Installing ACP 5 and connect-
ing cables
After setting PI485, the ACP 5 shall be
installed in an adequate place, and RS-485
cable shall be connected for the communica-
tion with PI485.
And, Ethernet cable (LAN cable) shall be con-
nected for the connection with internet or AC
Manager 5.
To fix the ACP 5, the following 2 methods
may be used.
Install in DIN RAIL or fix to the wall consider-
ing the environment of the site.
Power
LAN cable
!
CAUTION
If four times the power con-
nector for the connection, as
shown by using the right
connection, but please note
that an electric shock.
Use the designated parts
must be connected to a
power source.
• Connector manufacturers: PHOENIX
CONTACTPartNo: MVSTBR 2,5 / 2-ST-5,
08 2P 5.00 mm
PACP5A000
RS-485 cable
INSTALLING ACP 5
Installing the ACP 5 in DIN RAIL
ACP 5 can be installed in DIN RAIL with width
35 mm and height 7.5 mm.
Proceed as the follows to install the ACP 5 in
an adequate place.
The installation method of the ACP 5 is
explained here with the example of installing
the ACP 5 in DIN RAIL.
• Decide the space to install the ACP 5.
• Before installing the ACP 5, check if it is the
adequate place to connect the ACP 5 with
the power, RS-485, and LAN cable.
• Install DIN RAIL.
• Hook the top part of the ACP 5 on DIN RAIL.
• Push the main body of the ACP 5 until you
hear the sound of installation.
• Pull the ACP 5 to check if it is fixed.
!
CAUTION
• After installing to DIN RAIL, do not fix to
the wall using screws.
• ACP 5 may be damaged.
• DIN Rail fixing Screw Spec: M3, screw
head height 2.0 ~ 1.75 mm, screw head
diameter 7.0 ~ 5.5 mm
13
Hooking on
DIN RAIL
Fixing to DIN RAIL