1. Install battery modules. 2. Install the baffle bars. Installing Battery Packs The 6 kVA/10 kVA standard model can connect to one battery pack, and the long backup time model can connect to a maximum of 13 battery packs. Battery packs cannot be shared in a parallel system. Each of the positive and negative battery strings of the 15 kVA/20 kVA long backup time model needs to connect at least one battery pack.
Installing Cables Installing Cables Between Battery Packs and Battery Modules Installing Cables Between Battery Packs and a 6 kVA/10 kVA UPS 1. The two battery ports on a battery pack have been connected in parallel inside. Do not connect them in series. 2.
Page 4
UPS 1 battery port Battery pack Battery pack Battery pack … 1 ports 2 ports 13 ports UPS 1 battery string UPS n (2 ≤ n ≤ 4) battery port … Battery pack Battery pack Battery pack 1 2 ports 13 ports ports UPS n battery string...
Page 5
No. 1 battery No. 1 battery pack in the pack in the positive negative battery string battery string No. 2 battery No. 2 battery pack in the pack in the positive negative battery string battery string No. 3 battery No. 3 battery pack in the pack in the positive...
Page 6
No. 1 battery No. 1 battery pack in the pack in the positive negative battery string battery string No. 2 battery No. 2 battery pack in the pack in the positive negative battery string battery string No. 3 battery No. 3 battery pack in the pack in the positive...
Page 7
1. Remove the baffle plates from the top and rear 2. Remove the fastener of the fuse board. of the battery module. 3. Install the battery module and reinstall 4. Install battery cables at one side and bind the fastener of the fuse board with J2 the cables, as shown in the following figure.
Page 8
8. Install cable locks and an insulation film. 9. Reinstall the baffle plates on the top and rear of the battery module. Insulation film Cable lock Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China www.huawei.com...