Install The Bezel - PureStorage FlashArray //X R2 Quick Installation Manual

Advertisement

5. Connect Host, Replication, and Management Cables
Connect each controller (CT0 and CT1) to a separate storage area network (SAN) and replication fabrics (A and B in
Figure 9) to ensure redundancy.
Depending on the customer order, the quad-port mezzanine can be equipped with either an Ethernet or SAS card,
and the PCIe slots can be equipped with Fibre-Channel or Ethernet cards.
1. Use customer-supplied cables to connect host ports
ETH17
(labeled SAN in Figure 9) to SANs as directed by the customer. Leave unused ports unpopulated.
2. Connect customer-supplied 1-GbE cables to management ports
1-GbE replication.
3. Connect customer-supplied 10- or 25-GbE cables from ports
ure 9) to replication network switch ports.
4. If the controller has an Ethernet card in the quad-port mezzanine, you can connect
shelves. See the DirectFlash Shelf Quick Installation Guide for more information.
If the controller has a SAS card in the quad-port mezzanine, you can connect
shelves. See the Expansion Shelf Quick Installation Guide for more information.
5. After connecting, pull gently on the cables until you feel resistance to ensure they are secure.
Repeat steps 1–5 for the second controller.
Figure 9. FlashArray Controller Ports (QP ETH and FC PCIe Cards Shown)
40-0154-01
FlashArray
FC0
through
FC13
or
ETH4
through
ETH5
and
ETH10
ETH0
and ETH1. Alternatively, you can use
ETH2
and
ETH3
(labeled REPL A and REPL B in Fig-
ETH6
through
ETH9
SAS0
through
SAS3
to expansion
6. Unpack and Install Shelves
Unpack and install any DirectFlash shelves or expansion shelves. Refer to the DirectFlash Shelf Quick Installation Guide (for
DirectFlash shelves) or Expansion Shelf Quick Installation Guide (for 12G shelves) for unpacking, installation, and cabling
instructions. After installing DirectFlash shelves or expansion shelves, resume the installation procedure starting with "Install
the Bezel" below.

7. Install the Bezel

through
1. Remove the protective film on the front surface of the bezel.
ETH1
for
2. Install the bezel, aligning the power connector with the logo illumination socket on the front panel. See Figure 10.
Make sure the asset tag is fully inserted into the slot or you will be unable to install the bezel.
To remove the bezel, press the two fastening handles to disengage it from the front panel.
to DirectFlash
Page 4 of 6
Quick Installation Guide
Figure 10. Installing the Bezel
October 12, 2018