MAN0530 Issue 09 October 03
2104M0506
3. INSTALLATION AND OPERATION
(e)
When the SIG level has been maximised in one plane, make small adjustments in
the other plane until SIG has been maximised in this plane.
(f)
Repeat steps (b) to (e) until the SIG level has been maximised in both planes.
At this point, SIG must be bigger than the initial TGT level and any adjustment
either side of the current alignment must result in a reduction in signal level.
If not, repeat steps (b) to (e) until these requirements have been met.
(g)
Lock off the alignment by placing a hex (Allen) key in the pair of grub-screws
which control adjustment in a particular plane and simultaneously rotating them
inopposite directions.
(h)
Repeat this for the other pair of grub-screws.
(i)
Press Enter and the signal levels are checked.
With the SIG level is greater than the TGT level, the signal check should
pass and the screen should display the following message:
Notes:
1.
If SIG is less than the TGT value the following message is displayed:
2.
If SIG is more than the TGT value the screen shows the bar graph screen again.
(12)
When the following message is displayed press Enter:
The display changes to show the following instruction:
Ensure there is a gas-free atmosphere.
(13)
Press Enter on the keypad.
The following message is displayed for three seconds:
The following message is displayed for three seconds:
Signals OK
Low Signal
Enter to Retry
Signals OK
Ensure Zero Gas
Then Press Enter
Zero Calibration
OK
Installation
Complete
48
Searchline Excel