Prerequisites; Hardware And Software Components - Siemens SINAMICS S120 Getting Started

Starter commissioning tool
Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Prerequisites

This chapter describes the prerequisites for step-by-step configuration and com-
missioning.
The configuration and commissioning steps are described in detail in Chapters 3
and 5.
2.1

Hardware and software components

In our example, a drive unit is to be assembled for a motor.
The following components are required for the drive unit:
S Active line module
S Control unit CU320
S Motor module
S Sensor module SMC20
S Synchronous motor (e.g. 1FK6) or induction motor (e.g. 1PH7) with sensor
S DRIVE-CLiQ cables
You will also need line filters, line reactors for the active line module, motor, power,
and encoder cables, as well as a SITOP modular 24 V DC power supply, for exam-
ple.
The following prerequisites must be fulfilled before you start commissioning:
S CompactFlash card with firmware
S The components are wired by means of DRIVE-CLiQ
S The PROFIBUS interface control unit is connected to a PC/PG via a PROFI-
BUS interface
S The STARTER commissioning tool must be installed on your PC/PG
Note
For instructions on wiring the components, connecting the PROFIBUS interface to
a PC/PG, and installing the STARTER commissioning tool, see the Equipment
Manuals /GH1/ and /GH2/ and the Installation and Start-Up Manual /IH1/.
 Siemens AG, 2004. All rights reserved
SINAMICS S120 Getting Started with the STARTER Commissioning Tool – 04.2004 Edition
2
2-19

Advertisement

Table of Contents
loading

Table of Contents