10.2 WATER CONNECTION

20l/min.
clean water, to be kept full at all times, and from which water can
be taken by means of the self-priming pump supplied with the
machine. In this case the hose must have a minimum diameter
not be subject to deformation during use.
is connected to the tank, it must be activated by manually
The same operation must be repeated each time the circuit is
drained, or after a prolonged period of disuse.

10.3 AIR CONNECTION

Open the spray jet air valve.
10.4 CORRECT CONNECTIONS FOR MATERIAL LINES
Take the material hoses and check that they are in perfect condi-
tion, that the couplings are intact and all relative seals are present.
Check that the cam levers ( A ) of the couplings have been tightened
IMER INTERNATIONAL S.p.A.
KOINE 35
FIG.7
25
11. START-UP
Before starting up the machine, check that the air valve on the
spray jet is open (ref.9a).
Turn the main switch (ref.Q1) on the electrical panel to 1; the
compressor is activated. Using the two pushbuttons (ref.Q3),
access start command n°2(ref.Q4) on the display.
Remove the cap (ref 1a) and check that there is no material
obstructing the hole underneath. Press the supplementary water
-at 300 l/min for cement-based products
-at 500 l/min for gypsum based products
Load the hopper with the relative premixed material in sacks.
Set the cell wheel selector (ref.Q11) to the ON position.
Position the start selector (ref.Q5) to ON (rotate to the right), to
start up the machine.
Wait for material to be delivered from the jet and at the same time
load the material hopper.
At this point the mix delivered by the jet can be adjusted by cor-
recting the quantity of water as required.
to obtain the required consistency.
When the jet starts to deliver material at the required consistency,
normal work can be started.
The machine starts and stops by opening and closing the air
supply to the spray jet.
(see paragraph Errors, page 24): if one of these events occurs,
the thermal cut-out trips. In this case reset the switch (ref.Q5) and
turn the main switch to 1.
In the event of water pressure failure (see table
the motor shuts down and the green light turns off (ref.Q8). The ma-
To stop the machine in the event of an emergency, press the red
emergency button (ref.Q10) - all moving parts are shut down - then
turn the main switch to 0 and remove the electric power plug from
the mains socket.
),