Step 3e: Route the six secondary leads and the three connectors
forward and to the right out the end of the accessory tray for the
NF frame. For the RF frame, route the leads out as shown.
Figure 26. Step 3 (NF frame shown)
Figure 27. Step 3 (RF frame shown)
Step 4e: Place the left accessory tray with the installed OTS switches
back to its original position as shown. Be careful not to bind
secondary wires or connector plugs.
Figure 28. Step 4 (NF frame shown)
8
EATON www.eaton.com
Installation and removal instructions for Series NRX
undervoltage release, shunt trip, and overcurrent
trip switch in left accessory tray
Figure 29. Step 4 (RF frame shown)
N
otee:
The proper routing of leads will prevent the wires from being pinched
by the trip unit interlock plate in the RF frame breaker.
Step 5e: The installed left accessory tray should look as shown in
Figure 30 with secondary leads extending out behind the trip unit
mounting plate location. Secondary connections can now be made.
Accessory tray
installed
Figure 30. Step 5 (NF frame shown)
Step 6e: Make the appropriate secondary connections as outlined
in Section 6. If necessary, bundle secondary wires using industry-
accepted wire tie practices.
Step 7e: Replace the front cover and secure it in place with the four
mounting screws previously removed in Step 1.
Trip unit
interlock plate
Secondary connectors

Advertisement

Table of Contents
loading

This manual is also suitable for:

Nrx nfNrx rf

Table of Contents