Chapter 3: Deployment process

Deployment process

The following figure shows the deployment process for Avaya SBCE.
Figure 3: Deployment process

Deployment checklist

No.
Task
1.
Mount the server on an equipment rack or an electrically grounded table
top.
2.
High availability requires GARP support on the connected network
elements. In scenarios where GARP is not supported, use a GARP-
aware router or switch between the elements and Avaya SBCE for the
switch to handle GARP packets sent from Avaya SBCE.
3.
Connect the server to the existing network.
4.
(Optional) Prepare the USB device or a DVD for installing Avaya SBCE.
August 2015
Comments on this document? infodev@avaya.com
Notes
Applicable only to
multiple server HA
scenarios.
Perform steps 3
and 4 only if the
server does not
have the software
pre-installed.
Thumb drives are
shipped separately
if ordered by the
customer.