Installing The Tensioner - Martin PIT VIPER Installation Instructions Manual

Pre-cleaner
Table of Contents

Advertisement

5.2.2
© Martin Engineering GmbH
Fig. 2
5. Mark a point on the perpendicular which is at least 178 mm from
the centre (1, Fig. 2).
6. Draw a line vertical to the perpendicular at this point (2, Fig. 2).
7. The point of intersection (3, Fig. 2) with the arc of the circle is
the installation position of the pre-cleaner.
8. Repeat steps 1 to 7 on the far side of the chute wall.

Installing the tensioner

See the installation manual accompanying your Inline Reversing
tensioner for specific instructions on how to install it (Section 2.1.4).
2
3
16
178
90°
1
M3735UK-09/15