Test Delay Stop Option (if equipped)
Note:
The adjustable timer located inside the control cabinet is preset at the factory for 6-minutes.
1. While the system is running, push the Delay Stop Switch. The system should run for 6-minutes then
shut off.
2. Restart the system. Push the Delay Stop Switch, then push the Stop push button on the Start/Stop
station. The system should stop immediately.
Deodorizer Injector Option (if equipped)
Note:
The deodorizer injector pump speed control is located inside the remote control cabinet.
Consult a chemical supplier for the correct deodorizing chemical.
1. Deodorizer speed adjustments depend upon the customer's needs and the chemical recommended
by the chemical supplier; therefore, the factory cannot provide speed adjustment guidelines.
2. Place the chemical pick-up tube in the chemical container. The container must not be higher
than the injection point on the water extractor.
3. Push the Deodorizer Toggle Switch to ON. The deodorizer injector will run.
4. Turn the adjustment screw on the deodorizer speed control circuit board CW to increase the
injector motor speed or CCW to reduce the injector motor speed.
5. Push the deodorizer toggle switch to OFF. The deodorizer injector will stop.
The Deodorizer Power Switch is located on the
front of the remote control cabinet.
Pulper/Water Extractor- Initial Start-up
System Operation Tests
The Deodorizer Injector Speed Control Circuit board
is located in the top left corner
of the remote control cabinet.