iNstallatioN iNstruCtioNs
for all rEC N-PEak solar
PaNEls CErtifiEd aCCordiNg
to iEC 61215 & iEC 61730

Advertisement

Table of Contents
loading

Summary of Contents for REC N-PEAK Series

  • Page 1 N-Peak Series iNstallatioN iNstruCtioNs for all rEC N-PEak solar PaNEls CErtifiEd aCCordiNg to iEC 61215 & iEC 61730...
  • Page 2: Table Of Contents

    Fig. 14: Panel dimensions: REC N-Peak Black Series Fig. 7: Mounting hole specifications: REC N-Peak Fig. 15: MLPE device installation zones Fig. 8: Mounting hole installation example: REC N-Peak REC Installation Manual - N-Peak - IEC 61215 /61730 Rev C - 07.19 Ref: NE-06-22...
  • Page 3: Introduction

    This does not apply to damages due to a panel fault, in cases of loss of life, bodily injury or damage to health or in the event of a grossly negligent breach of obligations on the part of REC SOLaR PTE. LTD. and/or in the event of an intentional or grossly negligent breach of obligations by a legal representative or vicarious agent.
  • Page 4: Safety Measures

    PaNEl HaNdliNg In order to avoid damage to the solar cells and other components, all REC solar panels should be handled with care and protected from damage at all times. all warnings and instructions on the packaging should be observed. Follow these guidelines when unpacking, transporting, carrying, installing or storing panels: •...
  • Page 5: Electrical Installation

    The solar panels must not be exposed to artificially concentrated light. ENviroNMENtal faCtors REC solar panels are designed to provide decades of durable and stable output in installations up to 2000 m above sea level. ambient operating temperatures must be between -40° and +85°C.
  • Page 6: Panel Installation

    PaNEL INSTaLLaTION REC solar panels are designed for capturing solar radiation and are not suitable for use as overhead or vertical glazing. The IP rating of the junction box provides a level of protection that allows panels to be mounted in any orientation (see product technical specifications for exact rating).
  • Page 7: Mounting Methods: Clamping With Rails Parallel To The Short Side

    MouNtiNg MEtHods: ClaMPiNg WitH rails ParallEl to tHE sHort sidE REC N-Peak solar panels secured by clamping to mounting rails has been found to comply with IEC 61215 & IEC 61730 requirements for downward pressure,e.g., snow, of up to 7000 Pa (4666 Pa design load*) and upward pressure,e.g., wind, of up to 2400 Pa (1600 Pa design load*) according to the instructions below (*design loads apply a safety factor of 1.5 to the stated test load, e.g., test load 7000 Pa / 1.5 = 4666 Pa design load).
  • Page 8: Mounting Methods: Clamping With Rails Parallel To The Long Side

    MouNtiNg MEtHods: ClaMPiNg WitH rails ParallEl to tHE loNg sidE REC N-Peak solar panels secured by clamping to mounting rails has been found to comply with IEC 61215 & IEC 61730 requirements for downward pressure,e.g., snow, of up to 5400 Pa (3600 Pa design load*) and upward pressure,e.g., wind, of up to 2400 Pa (1600 Pa design load*) according to the instructions below (*design loads apply a safety factor of 1.5 to the stated test load, e.g., test load 5400 Pa / 1.5 = 3600 Pa design load).
  • Page 9: Mounting Methods: Slide In Systems

    MouNtiNg MEtHods: MouNtiNg HolEs REC N-Peak panels can be mounted utilizing the four elongated holes (11 x 6.6 mm) on the underside of the panel at a distance of 382.5 mm from the corner (fig. 6) in conjunction with a device, e.g., screws, lockbolts or structural blind fasteners, with specifications suitable for the installation (fig. 7).
  • Page 10: Drainage Holes

    HolEs Each corner of the REC panel frame has small drainage holes spaced 55 mm from the corner of the panel frame that allow water caused by rain, condensation, snow melt, cleaning or any other process to exit the frame easily and minimize damage caused by freezing and thawing (fig. 9). These holes must not be used for mounting the panel, and they must not be covered by any part of the mounting structure.
  • Page 11: Connections And Connectors

    CONNECTIONS aND CONNECTORS The connector type(s) used on REC solar panels are indicated in the product specifications at the rear of this manual. The connector IP rating is only valid when they are correctly connected. all connectors and cables must be secure and tight as well as electrically and mechanically sound.
  • Page 12: Maintenance

    The majority of the panel components can be recycled. For installations in the European Union, REC solar panels are subject to WEEE regulations. The symbol in fig. 12 as found on the label on the rear of the panel indicates that this product shall not be treated as household waste and must be disposed of at an appropriate collection point for the recycling of electrical and electronic equipment.
  • Page 13: Panel Characteristics

    IEC 62804, IEC 61701, IEC 62716, IEC 62782 ISO 9001: 2015, ISO 14001: 2004, OHSaS 18001: 2007 See warranty conditions for further details. take-e-way WEEE-compliant recycling scheme 1000 irradiance (W/m²) REC Installation Manual - N-Peak - IEC 61215 /61730 Rev C - 07.19 Ref: NE-06-22...
  • Page 14: Technical Properties: Rec N-Peak Black Series

    IEC 62804, IEC 61701, IEC 62716, IEC 62782 ISO 9001: 2015, ISO 14001: 2004, OHSaS 18001: 2007 See warranty conditions for further details. take-e-way WEEE-compliant recycling scheme 1000 irradiance (W/m²) REC Installation Manual - N-Peak - IEC 61215 /61730 Rev C - 07.19 Ref: NE-06-22...
  • Page 15: Annex 1: Installations On Water Platforms

    ENviroNMENt installation site • REC solar panels may only be installed on closed bodies of fresh water where water salinity does not exceed 25 mS/cm at 25°C (15 PSU). This specifically excludes mounting on sea and ocean applications. •...
  • Page 16: Annex 2: Installations Using Module Level Power Electronics

    Series; indicates type/name can include any of the suffixes: ECO, BLK, BLK2, Black, XV, Mono (M in product code), e.g., RECxxxTP2SM 72 XV; REC TwinPeak 2S Mono 72 XV. The object of the declaration described above is in conformity with the relevant Union harmonisation legislation: 2014/35/EU "Directive of the European Parliament and of the Council on the harmonisation of the laws of the Member States relating...
  • Page 17: Document History

    DOCUMENT HISTORY date revision reason 07.2018 First release 01.2019 Update to warranty conditions, addition of REC N-Peak Black Series 08.2019 Updated Datasheets REC Installation Manual - N-Peak - IEC 61215 /61730 Rev C - 07.19 Ref: NE-06-22...
  • Page 18 REC SolaR PtE. ltd. 20 tuaS South avENuE 14 SINgaPoRE 637312 SINgaPoRE tel: +65 6495 9228 Mail: post@recgroup.com www.recgroup.com REC Installation Manual - N-Peak - IEC 61215 /61730 Rev C - 07.19 Ref: NE-06-22...
  • Page 19 ‘retro-fit’ system made by third-party manufacturers. MLPE devices may be used on REC solar panels where desirable or mandatory (note that the certification testing of solar panels does not include testing with MLPE devices). When installing an MLPE device on an REC solar panel, follow the instructions provided by the device manufacturer and the instructions specific for REC solar panels given below.