Launching The Control Program - NT-MDT NTEGRA Spectra Instruction Manual

Platform, snom measuring head
Hide thumbs Also See for NTEGRA Spectra:
Table of Contents

Advertisement

7. Close the exit laser shutter.
This completes primary adjusting the detection channel.

3.7. Launching the Control Program

Before this procedure, all interconnections of electromechanical units of the instrument
are to be done according to the manual NTEGRA Spectra Probe NanoLaboratory
(Upright Configuration with Renishaw Spectrometer).
ATTENTION! Tighten up all connectors before turning the controllers on.
Disconnection of connectors during operation may cause damage to the
electronic components.
1. Switch the spectrometer on.
2. Switch on the main and the slave controllers with the toggle switches on the front
panel.
3. Switch on the computer.
ATTENTION! The controllers and the spectrometer must be on before
starting the Control program.
4. Start the Nova program.
Fig. 3-18. Image of the focused laser spot
located slightly below the center of the screen
Chapter 3. Preparing for Operation
33

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents