SUN2000L-(2KTL-5KTL)
User Manual
Grid Charge
Step 1 On the Home screen, choose Device maintenance > Energy control > Energy storage
control > Grid charge and perform the required operation.
Figure 6-14 Grid charge
Table 6-6 Parameter description of Grid charge
Parameter
Grid charge
----End

6.5 IPS Test (for Italy CEI0-21 Grid Code only)

Context
The Italy CEI0-21 grid code requires IPS check for the SUN2000L. During the self-check
process, the SUN2000L consecutively checks the protection thresholds and time for 10-min
overvoltage, level 1 overvoltage, level 1 undervoltage, level 1 overfrequency, and level 1
underfrequency. The SUN2000L shuts down after the check starts, and it restarts after the
check is successful.
Issue 05 (2019-06-06)
Description
The power grid will charge
the battery if Grid charge is
enabled.
If Grid charge function is
disabled by default, comply
with the grid charge
requirements stipulated in
local laws and regulations
when this function is
enabled.
Copyright © Huawei Technologies Co., Ltd.
6 System Commissioning
Value Range
Disable
Enable
70