Replacing components and plant changes
6.1 Failure and replacement of components
● The name of the replaced PC is used for the new PC.
● The same IP address is used for the new PC.
● The MAC address is adapted in the project.
Replacing the BATCH server
Follow the steps below to replace a BATCH server:
Step
1
2
3
Replacing the BATCH client
Follow the steps below to replace a BATCH client:
Step
1
2
3
4
6.1.5

Replacement of Route Control stations in runtime

Replacement of Route Control stations
When replacing Route Control stations, a distinction must made between:
● Replacing a Route Control server
● Replacing a Route Control client
Requirements
● The new PC contains the same hardware components.
● An image of the PCs to be replaced is used for the installation.
● The name of the replaced PC is used for the new PC.
● The same IP address is used for the new PC.
● The MAC address is adapted in the project.
194
What?
Replace the BATCH server.
On the engineering station: Open the BATCH configuration dialog, select PCell, download
BATCH server.
Start the BATCH server (BATCH server starts up as standby server).
What?
Close the BATCH Control Center.
Replace the BATCH client.
On the engineering station: Open the BATCH configuration dialog, select PCell, download
BATCH client.
Open the BATCH Control Center.