Erasing The Result Memory; Preparations In The Field; Commissioning Of The Test Set - Siemens Cerberus NW8005 Technical Manual

Data line test set
Table of Contents

Advertisement

14
Siemens Building Technologies
Cerberus Division
5.1.4

Erasing the result memory

Press keys simultaneously for longer than 1 sec.
Press key once again for confirmation
5.2

Preparations in the field

1. The data line must not be live.
2. All bus nodes must be removed from the data line. No electronic components must
be connected to the data bus.
3. The individual segments of the data link must be interconnected.
4. The SLT-22 device is connected to terminals "Pair1" near end.
5. The SLT-11 device is connected to terminals "Pair1" far end.
5.2.1

Commissioning of the test set

Connect test specimen
The devices are connected using the safety cables and safety clips supplied. Terminals
Pair1 are used on both devices.
The SLT-22 device is used as actuating device (Master) at the near end and the SLT-
11 device (Slave) at the far end.
e3180a.doc