FASTENING THE CABLE TO THE DRUM
1. Tape the cable end to prevent loosening of the core
wires.
2. Pass the cable through the hole in cable guard, over
the upper snatch block and then inside the winch.
3. Insert the cable from behind the roll of the drum
brake.
4. Pull the cable onto the drum from the left hand
side (the same side as the clutch lever).
5. Pass the cable end through the hole in the drum
plate, pull about 15 cm (6"), and insert under the
wedge of the cable lock device. See fig. 3.
6. Tighten the cable lock screw.
7. Winch the cable on the drum. REMEMBER THAT
THE CABLE HAS TO BE LOADED HEAVILY, WHEN
WINCHING THE CABLE BACK ON THE DRUM.
Do not use longer cable than needed. With correct
length you achieve good pulling strength and proper
winding of the cable.

PRE-OPERATION CHECKS

CABLE
Check that:
the cable is faultless (breakage risk).
there are no twists or kinks (breakage risk) in the
cable.
the cable has been properly fastened to the winch.
Fig. 3. Fastening the cable
FARMI 61
WINCH
Check that:
all the pins and lynch pins are in place.
all bolts and nuts have been tightened.
roller chain is tight.
the drum brake has been properly adjusted.
the clutch has been correctly adjusted.
lubrication is carried out correctly. See lubricating
instructions.
MOUNTING TO THE TRACTOR
Check that:
the tractor's top link point is locked. (with the help
of a support, if necessary).
the pins are properly secured.
the side limits are locked and slack removed from
the lifting arm.
the PTO-shaft is suitably long, properly fastened
and the shield chains attached.
the winch support legs have been raised.