Replacement Of Failed Components & Recommended Spares - Hamworthy Spetisbury Installation, Commisioning And Maintenance Instructions

Gas fired cast iron sectional boilers 100kw to 340kw
Table of Contents

Advertisement

14.0 REPLACEMENT OF PARTS
There are a number of components listed in Fig 14.1 which can be replaced simply and quickly by following the given
procedure. In each case the operation of each replaced component must be checked by carrying out the appropriate part
of the commissioning procedure. See Section 11.0: COMMISSIONING & TESTING.
NOTE: Isolate all electrical supplies to the burner and turn off the gas supply before removing covers and
commencing any servicing or component exchange procedure.
Figure 14.1 – Exploded View of Boiler
26
HAMWORTHY HEATING LTD
SPETISBURY
500001118/C

Advertisement

Table of Contents
loading

Table of Contents