Task 4: Verify Power Status - Cisco Expressway CE1200 Installation Manual

Hide thumbs Also See for Expressway CE1200:
Table of Contents

Advertisement

Cisco Expressway CE1200 Appliance Installation Guide
Install the Appliance
4.
The first boot takes approximately 5 minutes due to the initial power characterization test. Any subsequent
boot of the system takes approximately 2 minutes. The power characterization test displays the message
Performing Platform Characterization ... when running.
5.
If the power characterization test runs on subsequent bootups, causing a lag in the boot time, it is important
that you disable it. It is especially important to disable the test in a clustered environment to avoid issues. See
the
Appendix 1: Troubleshooting, page 19

Task 4: Verify Power Status

Check the Power Status LED on the front of the appliance:
Off. No AC power is present in the appliance.
Amber. Appliance is in standby power mode. Power is supplied only to the CIMC and some motherboard
functions.
Green. Appliance is in main power mode. Power is supplied to all server components.
Monitoring power consumption
The CIMC has a power monitoring utility that you can use to track power consumption.
section for more information.