Transport And Lifting Instructions - Genie DPL-25S Operator's Manual

Hide thumbs Also See for DPL-25S:
Table of Contents

Advertisement

Operator's Manual

Transport and Lifting Instructions

Observe and Obey:
Common sense and planning must be applied to
control the movement of the machine when
lifting it with a crane or forklift.
The transport vehicle must be parked on a level
surface.
The transport vehicle must be secured to
prevent rolling while the machine is being
loaded.
Vehicle capacity, loading equipment and
surfaces must be capable of supporting the
machine weight. See the serial plate for the
machine weight.
The machine must be secured to the transport
vehicle with chains or straps of ample load
capacity.
22
Loading the Machine With
a Forklift
1 Lower the platform.
2 Lower the platform side guard rails, the platform
end guard rail and the platform entry gate.
Secure the side guard rails with the tie-down
strap.
3 Push in the red Emergency Stop buttons at the
ground and platform controls, turn the key
switch to the off position and remove the key.
4 Inspect the entire machine for loose or
unsecured items.
5 Use the forklift pockets located on the sides of
the machine.
Winching the Machine onto a
Flatbed Truck
1 Lower the platform.
2 Lower the platform side guard rails, the platform
end guard rail and the platform entry gate.
Secure the side guard rails with the tie-down
strap.
3 Push in the red Emergency Stop buttons at the
ground and platform controls, turn the key
switch to the off position and remove the key.
4 Inspect the entire machine for loose or
unsecured items.
5 Connect the cable to the winching point (tie-
down points) located on the base.
6 Carefully winch the machine onto the truck.
7 Secure the machine base and masts to the
transport vehicle. Use chains or straps of ample
load capacity.
Genie DPL Super Series
Second Edition • First Printing
Part No. 82799

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dpl-30sDpl-35s

Table of Contents