The setup for the PAC5532EVK1 evaluation module requires up to four simple connections.
1. Connect the VIN power source via spade tab connectors VIN and GND. As VIN power is applied, the
LED D17 will light up. Once VIN voltage goes above 25V, the PAC5532's Multi Mode Power Manager
will be engaged and the VSYS (5V) regulator will be enabled. This event will result in LED D5 lighting
up.
2. Connect the 3 Phase BLDC/PMSM motor via spade tab connectors PHASE U, PHASE V and PHASE
W.
3. If Serial Communications are desired, connect the USB to UART module 4 pin connection to J4.
4. For debugging/programming, connect a suitable USB SWD module to J3 by using a standard 4 wire
cable.