To fix the encoder and prepare the connection cable of the electric signals, follow
the instructions of item 3.
For the correct installation of modules ENC-01 and ENC-02, follow the steps
below:
step 1: With the inverter de-energized, remove the front cover of the CFW11
(figure 2);
step 2: Carefully plug-in the module into slot 2 (figure 3(a));
step 3: Place and tighten the grounding screw and fixture of the module
(figure 3(b));
step 4: Set the module switches as shown in table 1;
step 5: Connect the encoder cables to connector XC4 of modules ENC-01 and
ENC-02.