GE SIGNA EXPLORER Installation Manual page 14

Table of Contents

Advertisement

9'-4"
16.2
1
2
MAGNET ROOM
CONTROL ROOM
Typical
SIGNA EXPLORER /SIGNA CREATOR
4
3
EQUIPMENT ROOM
EN-MRI-TYP-SIGNA_EXPLORER-WEB.DWG
ITEM
DESCRIPTION
Cryogen vent (200mm [8"] O.D.)
1
2
Emergency exhaust vent - refer to magnet room vent requirements (position to be defined)
Pressure equalization vent - refer to magnet room vent requirements (position in ceiling to be
3
defined)
(2) 13mm [1/2"] I.D. High pressure hoses and (4) 25mm [1"] compression clamps. 150 Micron
4
filter, Shut off valves and By-pass valve as required.
MECHANICAL/PLUMBING NOTES
All piping, fittings, supports, hoses, clamps, ventlation systems, etc. are to be supplied and installed
by the customer or his contractors.
For complete design and requirements, specifications and guidelines refer to the pre-installation
manual: system cooling, cryogen venting, waveguides and exhaust venting.
An emergency water cooling back-up supply is recommended for continuous cryogen compressor
operation. if using an open loop back-up design, ensure a drain is provided. please refer to the
pre-install manual for optional back-up coolant supply requirements
Rev
A
Date
03/Aug/2018
M1 - Mechanical Layout
14
/24