JCM GLOBAL UBA-RC Series Operation And Maintenance Manual

JCM GLOBAL UBA-RC Series Operation And Maintenance Manual

Banknote recycler
Table of Contents

Advertisement

website: http://www.jcmglobal.com
UBA-RC
Series
Banknote Recycler
Operation and Maintenance
Manual
(Revision 3)
P/N 960-100928R_Rev. 3 {EDP #192692}
Issue #4088-SME-01-03
© 2018, JAPAN CASH MACHINE CO., LTD.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the UBA-RC Series and is the answer not in the manual?

Questions and answers

Summary of Contents for JCM GLOBAL UBA-RC Series

  • Page 1 website: http://www.jcmglobal.com UBA-RC Series ™ Banknote Recycler  Operation and Maintenance Manual (Revision 3) P/N 960-100928R_Rev. 3 {EDP #192692} Issue #4088-SME-01-03 © 2018, JAPAN CASH MACHINE CO., LTD.
  • Page 2 UBA-RC™ Series Banknote Recycler Operation and Maintenance Manual Issue #4088-SME-01-03 REVISION HISTORY Date Reason for Update Comment Rev N 10/24/11 Initial Version Specification, Exploded View, Parts Lists and Copyright changes 12/30/13 per JCM Engineering and Technical Support recommendations 9/16/15 Updated Product Descriptions, Parts Lists Updated Product Descriptions in Section 1 and updated Parts Lists 2/7/18 in Section 7...
  • Page 3: Table Of Contents

    UBA-RC™ Series Banknote Recycler Table of Contents Page 1 GENERAL INFORMATION ................. 1-1 Description ........................1-1 UBA-RC Unit Assembly ..................... 1-1 Model Descriptions ....................1-2 Type Descriptions ....................... 1-2 Software Descriptions ....................1-2 Precautions ......................... 1-2 User Cautions ...........................1-3 Installation Cautions ......................1-3 Mounting, Dismounting &...
  • Page 4 UBA-RC™ Series Banknote Recycler Table of Contents Page Restoring Banknotes Directly into the Recycler Unit ............. 2-6 Retrieving Banknotes ....................2-6 Sending Retrieved Banknotes to the Cash Box ............... 2-6 Sending Retrieved Banknotes to the Cash Box by Command ..........2-6 Retrieving Banknotes Directly ....................
  • Page 5 UBA-RC™ Series Banknote Recycler Table of Contents Page Pick Roller Removal ....................4-8 Feed Roller Removal ....................4-9 Impeller and Stop Roller Removal ................4-10 O-Ring (Pusher Plate) Removal ................4-11 Roller Timing Belt and O-Ring Removal ..............4-11 Pusher Plate Re-installation ....................4-12 5 WIRING DIAGRAMS ...................
  • Page 6 UBA-RC™ Series Banknote Recycler Table of Contents Page UBA-RC Frame Unit 5 Parts List ................... 7-12 UBA-RC RC Space 1 Exploded View ..............7-13 UBA-RC RC Space 1 Parts List ..................... 7-14 UBA-RC RC Space 2 Exploded View ..............7-15 UBA-RC RC Space 2 Parts List .....................
  • Page 7 UBA-RC™ Series Banknote Recycler Table of Contents Page Maintenance Equipment Requirements ..............A-6 Additional UBA-RC Maintenance Equipment ................A-6 Reference Paper Handling ...................... A-6 B GLOSSARY ......................B-1 P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD.
  • Page 8 UBA-RC™ Series Banknote Recycler Table of Contents THIS PAGE INTENTIONALLY LEFT BLANK P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD.
  • Page 9 UBA-RC™ Series Banknote Recycler List of Figures Page Figure 1-1 UBA-RC Unit Assembly ................ 1-1 Figure 1-2 Precautionary Symbols ................. 1-2 Figure 1-3 Unacceptable Banknotes ..............1-4 Figure 1-4 Banknote Storage Insertion Cautions ........... 1-4 Figure 1-5 UBA-RC Component Names ..............1-5 UBA-RC Banknote Recycler Standard Unit with Bezel ...
  • Page 10 UBA-RC™ Series Banknote Recycler List of Figures Page Figure 4-6 Lifter Motor Bracket Removal ..............4-3 Figure 4-7 Lifter Motor Assy Removal ..............4-3 Figure 4-8 Rear Frame & Middle Frame Removal ..........4-3 Figure 4-9 Rear Transport Assy Removal .............. 4-4 Figure 4-10 Left Frame Plate Removal ..............
  • Page 11 UBA-RC™ Series Banknote Recycler List of Figures Page Figure 6-1 Tool and Harness Connection ...............6-1 Figure 6-2 setup.exe Location ................6-1 Figure 6-3 Install Shield Wizard Screen..............6-1 Figure 6-4 Installation File Extracting Screen ............6-2 Figure 6-5 Customer Information Screen..............6-2 Figure 6-6 Destination Folder Screen ..............6-2 Figure 6-7 Current Settings Confirmation ...............6-2...
  • Page 12 UBA-RC™ Series Banknote Recycler List of Figures Page Figure 6-45 Loading Model Information Screen 2 ............ 6-9 Figure 6-46 Version Information Screen 1..............6-9 Figure 6-47 Version Information Screen 2..............6-9 Figure 6-48 Sensor Test Selection ................. 6-10 Figure 6-49 Test Function Listing Screen............... 6-10 Figure 6-50 Calibration Test Function Screen Buttons...........
  • Page 13 UBA-RC™ Series Banknote Recycler List of Tables Page Table 1-1 UBA-RC Model Number Specifications ..........1-2 Table 1-2 UBA-RC Type Specifications ..............1-2 Table 1-3 UBA-RC Software No. Specifications ........... 1-2 Table 1-4 UBA-RC Technical Specifications ............1-6 Table 1-5 UBA-RC Environmental Specifications ..........
  • Page 14 UBA-RC™ Series Banknote Recycler List of Tables Page Table 7-19 WBA-SH2 Cash Box Parts List 2 ............7-35 Table 7-20 WBA-SH2 Cash Box Parts List 3 ............7-36 Table 7-21 WBA-SH2 Cash Box Parts List 4 ............7-38 Table 7-22 WBA-SH2 Cash Box Parts List 5 ............7-40 Table 7-23 UBA-RC Large Cash Box Frame Unit Parts List .........
  • Page 15: Uba-Rc™ Series

    UBA-RC™ Series Banknote Recycler S e c t i o n 1 1 GENERAL INFORMATION Description In order to make operation of this device easier and This section provides a general overview of the  make navigation within this manual simpler, the Series Banknote Recycler Unit ...
  • Page 16: Model Descriptions

    Section 1 UBA-RC™ Series Banknote Recycler General Information Model Descriptions Table 1-2 UBA-RC Type Specifications Table 1-1 lists the Product Model Number Type: * 0 0 - 0 0 - * * 1 * * * * * * * * descriptions.
  • Page 17: User Cautions

    General Information UBA-RC™ Series Banknote Recycler Section 1 Preventive Maintenance User Cautions Careful measures are taken in the design of this The Preventive Maintenance requirements are product to ensure its quality; however, the follow- defined as follows: ing cautions should be read and understood by all 1.
  • Page 18: Banknote Fitness Requirements

    Section 1 UBA-RC™ Series Banknote Recycler General Information Banknote Fitness Requirements 7. Make sure the denomination of each Banknote bundle inserted is correctly placed in the same The following Banknote types may not validate direction. correctly, or can cause a Banknote jam and/or dam- 8.
  • Page 19: Component Names

    General Information UBA-RC™ Series Banknote Recycler Section 1 Component Names Figure 1-5 illustrates the UBA-RC component names and locations. ™ Figure 1-5 UBA-RC Component Names C: Front Panel Access Door NOTE: The Front Panel Access Door should NOT BE LEFT OPEN when the UBA-RC Bin Assembly is re-installed into the Frame.
  • Page 20: Specifications

    Section 1 UBA-RC™ Series Banknote Recycler General Information Specifications Technical Specifications Table 1-4 UBA-RC Technical Specifications 98% or greater The following Banknote Types are excluded: a) Banknotes with excess or poor magnetism or unclear graphics Acceptance Rate: b) Double (dual) Banknotes c) Worn, dirty, wet, stained, torn or excessively-wrinkled Banknotes d) Banknotes having folded corners or edges e) Banknotes having the wrong cut dimensions or a printing displacement...
  • Page 21: Environmental Specifications

    General Information UBA-RC™ Series Banknote Recycler Section 1 Environmental Specifications Table 1-5 UBA-RC Environmental Specifications Operating Temperature: 5ºC to +50ºC (41ºF to 122ºF) Storage Temperature: -20ºC to +60ºC (-4ºF to 140ºF) Relative Operating Humidity: 30% to 85% RH (non-condensing) Relative Storage Humidity: 30% to 85% RH (non-condensing) Visible Light Sensitivity: Avoid contact with direct Sunlight...
  • Page 22: Unit Dimensions

    Section 1 UBA-RC™ Series Banknote Recycler General Information Unit Dimensions Entire Unit Outside Dimensions Figure 1-6 illustrates the UBA-RC Unit with the Bezel, Bezel Spacer and 400 Note Cash Box outside ™ dimensions. Figure 1-6 UBA-RC Banknote Recycler Stan- 25.1 31.2 dard Unit with Bezel Outside Dimensions 87.4...
  • Page 23: Entire Unit Outside Dimensions (Continued)

    General Information UBA-RC™ Series Banknote Recycler Section 1 Entire Unit Outside Dimensions (Continued) Figure 1-8 illustrates the UBA-RC Unit with the Bezel, Bezel Spacer and 800 Note Cash Box outside ™ dimensions. Figure 1-8 UBA-RC Banknote Recycler Stan- 25.1 31.2 87.4 UBA Bezel Unit dard Unit with Bezel Outside Dimensions...
  • Page 24: Technical Contact Information

    Section 1 UBA-RC™ Series Banknote Recycler General Information Technical Contact Information To obtain further technical information regarding the UBA-RC device, please contact the nearest loca- ™ tion listed below: Asia and Oceania Americas JCM G (HK) L JCM A MERICAN Phone: +852-2429-7187 Phone: +1-702-651-0000 Fax: +852-2929-7003...
  • Page 25: Installation

    UBA-RC™ Series Banknote Recycler S e c t i o n 2 2 INSTALLATION This section provides installation and operating 3. When a bottom mounting configuration is pre- ferred, bolt the inside or outside of the UBA-RC ™ instructions for the UBA-RC Series Banknote ™...
  • Page 26: Cable Interconnection

    Section 2 UBA-RC™ Series Banknote Recycler Installation Cable Interconnection Table 2-2 UBA-RC Unit DIP Switch Settings Figure 2-3 illustrates the Cable interconnection UBA-RC Unit DIP Switches requirements between the UBA-RC and a Host ™ Machine. Figure 2-3 Cable Interconnection Switch Switch ON Switch OFF Reserved...
  • Page 27: Connector Pin Assignments

    Installation UBA-RC™ Series Banknote Recycler Section 2 Connector Pin Assignments Table 2-3 lists the Photo Coupler Interface Connector Pin Assignments. Table 2-3 Photo Coupler Interface Connection Pin Assignments Socket (Transport Unit Side): DRA-20PC-FO (JAE) Contact (Transport Unit Side): D02-22-26P-10000 (JAE) Socket (Frame Side): DRA-20SC-FO (JAE) Contact (Frame Side): D02-22-26S-10000 (JAE)/D02-22-22S-10000 (JAE) (Terminal# 3, 13) Recommended Wires: Slit Wire UL1061 AWG #26...
  • Page 28: Connector Pin Assignments (Continued)

    Section 2 UBA-RC™ Series Banknote Recycler Installation Connector Pin Assignments (Continued) Table 2-4 lists the RS232C Interface Connector Pin Assignments. Table 2-4 RS232C Interface Connection Pin Assignments Socket (Transport Unit Side): DRA-20PC-FO (JAE) Contact (Transport Unit Side): D02-22-26P-10000 (JAE) Socket (Frame Side): DRA-20SC-FO (JAE) Contact (Frame Side): D02-22-26S-10000 (JAE)/D02-22-22S-10000 (JAE) (Terminal# 3, 13) Recommended Wires: Slit Wire UL1061 AWG #26 Pin No.
  • Page 29: Connector Pin Assignments (Continued)

    Installation UBA-RC™ Series Banknote Recycler Section 2 Connector Pin Assignments (Continued) Table 2-5 lists the UBA-RC Power Supply Pin Assignments. ™ Table 2-5 Power Supply Pin Assignments Header Type: 53426-0410 (MOLEX) Contact Type: 50351-8100 (MOLEX) Housing: 51103-0400 (MOLEX) Recommended Wires: Slit Wire UL1007 AWG #22-24 Pin No.
  • Page 30: Preventive Maintenance

    Section 2 UBA-RC™ Series Banknote Recycler Installation Preventive Maintenance 2. Press the Restore Pushbutton on the Recycler Unit (Review Figure 1-5 G). Restoring Banknotes  NOTE: The Banknotes in the RC1-Bin Space and the RC2-Bin To restore Banknotes into the Recycle Unit, per- Space will be retrieved note-by-note form one (1) of the following two (2) procedures: into the Cash Box.
  • Page 31: Dispense Settings

    Installation UBA-RC™ Series Banknote Recycler Section 2 Dispense Settings 6. If the Banknote jam location is still not visible, pull the Cash Box out of the Frame (Figure 2-7 e) Dispensing Banknotes from the RC1-Bin Space and remove the jammed Banknote from inside the and/or the RC2-Bin Space of the Recycler Unit is Frame Unit (Figure 2-8 d).
  • Page 32 Section 2 UBA-RC™ Series Banknote Recycler Installation Caution: DO NOT use alcohol, solvents, abrasive cleaning agents, or citrus- based cleaners that can damage the plastic surface of the device when cleaning it. The lenses can become clouded by chemical evaporation residue that may cause acceptance errors.
  • Page 33: Sensor And Roller Locations

    Installation UBA-RC™ Series Banknote Recycler Section 2 Sensor and Roller Locations Unit’s sensor cleaning locations. Table 2-7 lists the  Figure 2-10 illustrates the various UBA-RC ™ UBA-RC sensor type cleaning methods, respectively. ™ Figure 2-10 UBA-RC Sensor, Roller and Belt Cleaning Locations NOTE: Remove the Recycler Unit and clean the enclosed Blue...
  • Page 34: Standard Interface Circuit Schematics

    Section 2 UBA-RC™ Series Banknote Recycler Installation Standard Interface Circuit Schematics Figure 2-11 illustrates the UBA-RC Photo-Coupler Circuit Interface Schematic Diagram. ™ Figure 2-11 UBA-RC Photo-Coupler Circuit Controller Side Validator Side Interface Schematic Diagram 4.7K 2.2K 1SS352 4.7K PC357 XJ8B-0311 1SS352 MRESET MRESET...
  • Page 35: Operational Flowcharts

    Installation UBA-RC™ Series Banknote Recycler Section 2 Operational Flowcharts Figure 2-14 depicts a typical UBA-RC Primary Sequence flow process. ™ Figure 2-14 UBA-RC Operational Flowchart (Primary Sequence) Power ON Apply Power to the Unit. a) Initializing A) Return from “h” or “d” in this Flow b) Stand-by c) Is Acceptance inhibited? d) External LED extinguished...
  • Page 36: Operational Flowcharts (Continued 1)

    Section 2 UBA-RC™ Series Banknote Recycler Installation Operational Flowcharts (Continued 1) Figure 2-15 depicts a typical UBA-RC Validation flow process. ™ Figure 2-15 UBA-RC Operational Flowchart B1) Return from Figure 2-14 “Primary Sequence”  (Validation) Flow on page 2-11 of this Service Manual D2) Return from Figure 2-16 “Validation Retry”...
  • Page 37: Operational Flowcharts (Continued 2)

    Installation UBA-RC™ Series Banknote Recycler Section 2 Operational Flowcharts (Continued 2) Figure 2-16 depicts a typical UBA-RC Validation Retry flow process. ™ Figure 2-16 UBA-RC Operational Flowchart D1) Return from Figure 2-15 “Validation” Flowchart  (Validation Retry) on page 2-12 of this Service Manual a) Was Validation retried twice? (*1) b) Return the Banknote D2) Return to the Figure 2-15 “Validation”...
  • Page 38: Operational Flowcharts (Continued 3)

    Section 2 UBA-RC™ Series Banknote Recycler Installation Operational Flowcharts (Continued 3) Figure 2-17 depicts a typical UBA-RC Recycler Stacking flow process. ™ Figure 2-17 UBA-RC Operational Flowchart C1) Return from Figure 2-15 “Validation” Flow on (Stacking/Recycle Unit) page 2-12 of this Service Manual a) Transporting the Banknote to the Recycler Unit b) Is the Banknote transporting? c) Was transportation retried three (3) time?
  • Page 39: Operational Flowcharts (Continued 4)

    Installation UBA-RC™ Series Banknote Recycler Section 2 Operational Flowcharts (Continued 4) Figure 2-18 depicts a typical a UBA-RC Cash Box Stacking flow process. ™ Figure 2-18 UBA-RC Operational Flowchart C2) Return from the Figure 2-15 “Validation” Flow on (Stacking/Cash Box) page 2-12 of this Service Manual a) Sending the Banknote to the Cash Box b) Is the Banknote being sent to the Cash Box?
  • Page 40: Operational Flowcharts (Continued 5)

    Section 2 UBA-RC™ Series Banknote Recycler Installation Operational Flowcharts (Continued 5) Figure 2-19 depicts a typical UBA-RC Dispensing flow process. ™ Figure 2-19 UBA-RC Operational Flowchart C2) Return from the Figure 2-14 “Primary Sequence”  (Dispensing) Flow on page 2-11 of this Service Manual a) Transporting the Banknote b) Collecting the Banknote data c) Is the Banknote abnormal condition?
  • Page 41: Operational Flowcharts (Continued 6)

    Installation UBA-RC™ Series Banknote Recycler Section 2 Operational Flowcharts (Continued 6) Figure 2-20 depicts a typical UBA-RC Abnormal Banknote Detection during Dispense flow process. ™ Figure 2-20 UBA-RC Operational Flowchart E) Return from the Figure 2-19 “Dispensing” Flow (Abnormal Banknote Detection when chart on page 2-16 of this Service Manual Dispensing) a) Is the Banknote condition abnormal? (Tried twice)
  • Page 42: Operational Flowcharts (Continued 7)

    Section 2 UBA-RC™ Series Banknote Recycler Installation Operational Flowcharts (Continued 7) Figure 2-22 depicts a typical UBA-RC Retrieving to Cash Box flow process. ™ Figure 2-22 UBA-RC Operational Flowchart C3) Return from the Figure 2-20 “Abnormal Banknote (Retrieving to Cash Box) Detection in Dispensing”...
  • Page 43: Communications

    UBA-RC™ Series Banknote Recycler S e c t i o n 3 3 COMMUNICATIONS This section was intentionally left out due to a Non-Disclosure Agreement requirement. If this information is required, please contact the closest office location listed below: Americas Asia and Oceania JCM A JCM G...
  • Page 44 Section 3 UBA-RC™ Series Banknote Recycler Communications THIS PAGE INTENTIONALLY LEFT BLANK P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 3 - 2...
  • Page 45: Disassembly/Reassembly

    UBA-RC™ Series Banknote Recycler S e c t i o n 4 4 DISASSEMBLY/REASSEMBLY Power Source Board Removal This section provides disassembly and reassembly instructions for the UBA-RC Series Banknote ™ To remove the Power Source Circuit Board, pro- Recycler Unit (UBA-10/12-SH2/SS-RC; UBA- ceed as follows: ).
  • Page 46: Recycler Cpu Board Assy Removal

    Section 4 UBA-RC® Series Banknote Recycler Disassembly/Reassembly Figure 4-2 Lifter Motor Encoder Circuit Board Figure 4-4 Recycler CPU Circuit Board Assembly Removal Removal Figure 4-2 Lifter Motor Encoder Circuit Board Assembly Removal Recycler CPU Board  Assy Removal To remove the Recycler CPU Circuit Board Assem- bly, proceed as follows: 1.
  • Page 47: Lifter Motor Assy Removal

    Disassembly/Reassembly UBA-RC™ Series Banknote Recycler Section 4 NOTE: Ensure that the Parallel Pin Figure 4-5 Emission Side Double Note Sensor (Figure 4-7 c) does not fall out when Removal removing the Gear. 3. Remove the two (2) Mounting Screws (Figure 4-7 &...
  • Page 48: Upper & Lower Full Sensor Led/ Upper & Lower End Sensor Pt/ Lifter Home Position Sensor Led & Pt Removal

    Section 4 UBA-RC® Series Banknote Recycler Disassembly/Reassembly 3. Tilt the Rear Transport Assembly (Figure 4-9 a) 6. Remove the four (4) Sensor Covers (Figure 4-12 backward and out of the Frame. ); the Upper & Lower Full Sensor PTs (Figure 4-12 &...
  • Page 49: Upper & Lower Flapper Pusher Lever Solenoid Removal

    Disassembly/Reassembly UBA-RC™ Series Banknote Recycler Section 4 4-13 e) in place, and separate the Frame Guide 3 NOTE: When re-assembling both from the Right Frame. the Upper and Lower Flapper 3. Remove the six (6) Sensor Covers (Figure 4-14 Solenoids, pull upward in the ) and remove the Upper &...
  • Page 50: Banknote Transaction Sensor/Transport Unit Encoder Board & Double Note Sensor Pt Removal

    Section 4 UBA-RC® Series Banknote Recycler Disassembly/Reassembly Figure 4-17 Banknote Transaction Sensor/ Figure 4-16 Flapper Open/Close Circuit Board Transport Unit Encoder Circuit Board & Double Removals Note Sensor Removal Figure 4-17 Banknote Transaction Sensor/ Transport Unit Encoder Circuit Board Figure 4-16 Flapper Open/Close Circuit &...
  • Page 51: Recycler Encoder Board Removal

    Disassembly/Reassembly UBA-RC™ Series Banknote Recycler Section 4 Recycler Encoder Board Removal Upper & Lower Recycler Transport Motor Assy Removal To remove the Recycler Encoder Circuit Board, proceed as follows: To remove the Recycler Transport Motors, proceed 1. Remove each of the four (4) Mounting Screws as follows: (Figure 4-19 &...
  • Page 52: Timing Belt Removal

    Section 4 UBA-RC® Series Banknote Recycler Disassembly/Reassembly Timing Belt Removal Figure 4-23 Timing Belt Cover Removals To remove the Timing Belt, proceed as follows: 1. Remove the two (2) Mounting Screws (Figure 4- & ) retaining the Rear Transport Upper Frame (Figure 4-22 b) in place, and take the Rear Transport Upper Frame off of the Rear Transport Assembly.
  • Page 53: Feed Roller Removal

    Disassembly/Reassembly UBA-RC™ Series Banknote Recycler Section 4 Feed Roller Removal Figure 4-25 RC Centering Guide Removal To remove the Feed Roller, proceed as follows: 1. Remove the four (4) Mounting Screws (Figure 4- ) retaining the RC Transport Race (Fig- ure 4-28 b) in place, and remove the Race from the Cash Box Unit.
  • Page 54: Impeller And Stop Roller Removal

    Section 4 UBA-RC® Series Banknote Recycler Disassembly/Reassembly Figure 4-30 Feed Roller Removal Figure 4-32 Spring Removals Figure 4-30 Feed Roller Removal Impeller and Stop Roller Removal Figure 4-32 Spring Removals To remove the Impeller and the Stop Roller,  3. Remove the four (4) E-Rings (Figure 4-33 proceed as follows: ) retaining the two (2) Shafts (Figure 4-33 &...
  • Page 55: O-Ring (Pusher Plate) Removal

    Disassembly/Reassembly UBA-RC™ Series Banknote Recycler Section 4 NOTE: Position the Impeller on the Figure 4-36 O-Ring Removals slotted portion of the Shaft when re- installing (Figure 4-34 & NOTE: Be sure that the Impeller wing’s direction is tilted toward the front, and that both sides of the wings are set in a parallel position as shown in the Figure 4-34 re-...
  • Page 56: Pusher Plate Re-Installation

    Section 4 UBA-RC® Series Banknote Recycler Disassembly/Reassembly 6. Remove the two (2) Pulleys (Figure 4-42 & Figure 4-38 Pusher Drive Gear Removal Phillips Self from the Shaft (Figure 4-42 b), and remove the Tapping six (6) O-Rings (Figure 4-42 ) from the individual Pulleys.
  • Page 57: Wiring Diagrams

    UBA-RC™ Series Banknote Recycler S e c t i o n 5 5 WIRING DIAGRAMS This chapter provides the UBA-RC Series • System Wiring Diagram ™ Banknote Recycler (UBA-10/12-SH2/SS-RC; • Transport & Partial Frame Unit Wiring UBA-RC ) Unit wiring diagrams for the following ™...
  • Page 58: Transport Unit & Frame Unit Wiring Diagram (Partial)

    Section 5 UBA-RC™ Series Banknote Recycler Wiring Diagrams Transport Unit & Frame Unit Wiring Diagram (Partial) Figure 5-2 UBA-RC Transport Unit/Frame Unit System Wiring Diagram (Part 1) 13V Output +13V 13V I/F MRESET +13V +24V MAIN RESE T +24V I/F GND 13V I/F +13V Frame...
  • Page 59: Figure 5-3 Uba-Rc Frame Unit System Wiring Diagram (Part 2)

    Wiring Diagrams UBA-RC™ Series Banknote Recycler Section 5 RAME IRING IAGRAM ARTIAL Figure 5-3 UBA-RC Frame Unit System Wiring Diagram (Part 2) Frame Unit (Part 2) Frame Unit Recycler Board Power Harness +13V +13V 13V I/F 13V I/F Connect to the ICE for Software Debug MRESET MRESET MAIN RESE T...
  • Page 60 Section 5 UBA-RC™ Series Banknote Recycler Wiring Diagrams THIS PAGE INTENTIONALLY LEFT BLANK P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 5 - 4...
  • Page 61: Performance Tests

    UBA-RC™ Series Banknote Recycler S e c t i o n 6 6 PERFORMANCE TESTS JCM Tool Suite Standard  This section provides Calibration and Performance Testing instructions for the UBA-RC Series ™ Edition Installation Banknote Recycler (UBA-10/12-SH2/SS-RC; Perform the following steps to install the JCM Tool ) Unit and contains the following ...
  • Page 62: Figure 6-4 Installation File Extracting Screen

    Section 6 UBA-RC™ Series Banknote Recycler Performance Tests 5. Confirm that the Installation File was extracted 9. Check the “ ” Area (Figure 6-7 a), Current Settings automatically (Figure 6-4). and click on the “ ” Screen Button Install (Figure 6-7 b) to begin the installation process. Figure 6-4 Installation File Extracting Screen Figure 6-7 Current Settings Confirmation Figure 6-4 Installation File Extracting Screen...
  • Page 63: Jcm Tool Suite Standard Edition

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 JCM Tool Suite Standard Edition Figure 6-13 DIP Switch Location When the “ ” is JCM Tool Suite Standard Edition installed, the Short-cut Icon shown in Figure 6-10 will appear on the PC Desktop. Figure 6-10 JCM Tool Suite Short-cut Icon Figure 6-10 JCM Tool Suite Short-cut Icon Figure 6-13 DIP Switch Location...
  • Page 64: Figure 6-19 Download Progress Screen

    Section 6 UBA-RC™ Series Banknote Recycler Performance Tests loading is complete, and the UBA Transport ™ Figure 6-16 Select Firmware 1 Unit LED will then start alternately flashing at a Color rate.  Green If “ ” is selected from the “ ”...
  • Page 65: Calibration

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 UBA-RC Reference Paper 17. Remove power from the UBA-RC. Set all the UBA-RC Transport DIP Switches to Figure 6-22 illustrates the KS-087 UBA-RC Ref- ™ erence Paper. Figure 6-21 Download Completed Screen Figure 6-22 KS-087 Reference Paper Figure 6-22 KS-087 Reference Paper Placing the Reference Paper...
  • Page 66: Figure 6-24 Uba Transport Dip Switch Setting

    Section 6 UBA-RC™ Series Banknote Recycler Performance Tests 10. Upon selection the “ ” UBA-RC Maintenance Tool Figure 6-24 UBA Transport DIP Switch Setting Screen shown in Figure 6-29 will launch automat- ically. 11. Click on the “ ” Screen Start Button (Figure 6-29 a) to begin the Calibration Figure 6-24 UBA Transport DIP Switch Setting...
  • Page 67: Figure 6-32 Uba-Rc Maintenance Tool Screen 4

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 15. Remove the KS-087 Reference Paper from the Figure 6-33 UBA-RC Maintenance Tool Screen Validator Head. 16. Confirm that the message “ Double Note Detection ” (Figure 6-32 a) Sensor Validation Success. appears in the upper Text Field area of the Screen.
  • Page 68: Model Information Confirmation

    Section 6 UBA-RC™ Series Banknote Recycler Performance Tests Model Information Confirmation Figure 6-36 UBA-RC Maintenance Tool Screen Perform the following steps to confirm the UBA- Unit’s Model Information. ™ 1. On the “ ” Screen, UBA-RC Maintenance Tool click on the “ ”...
  • Page 69: Reading The Model Information

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 Figure 6-42 Model Information Saving Com- Figure 6-45 Loading Model Information Screen pleted Screen Figure 6-42 Model Information Saving Completed NOTE: The Saved Model Information shown is the default information. Screen Figure 6-45 Loading Model Information Screen 2 Screen ...
  • Page 70: Individual Calibration And Performance Test

    Section 6 UBA-RC™ Series Banknote Recycler Performance Tests Individual Calibration and  Figure 6-50 Calibration Test Function Screen Performance Test Buttons This portion explains the individual Calibration and Performance Testing Procedures for each Sensor within an UBA-RC Unit. (Review “Sensor Cali- ™...
  • Page 71: Individual Performance Test

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 word will again turn to Grayed-out Figure 6-53 RC Full Sensor text (Figure 6-52 b). 5. Click on the “ ” Save Sensor Data Function Screen Button (Figure 6-52 c) to reflect the saved Status in the related result Field.
  • Page 72 Section 6 UBA-RC™ Series Banknote Recycler Performance Tests ) during the Performance Test, then NOTE: The Test Status will not appear in the appears grayed-out once the Test is complete Status Text Field unless the “Get All Sensor ). The UBA-RC LED will appear solid ™...
  • Page 73: Get All Sensor State

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 ENSOR TATE Table 6-3 Get All Sensor State Configurations Status Text Field Indication Item Description Detected Detected Detects a Banknote’s existence on the Double Note Detection Sensor (Does Double (Transport) not detect double Banknotes) Transport Sensor 1 Detects a Banknote’s existence on Transport Sensor 1 Transport Sensor 2...
  • Page 74: Performance Test Without A Pc

    Section 6 UBA-RC™ Series Banknote Recycler Performance Tests Performance Test without a PC Table 6-4 lists the Performance Test Items and the DIP Switch Settings for the Performance Test without using a PC for testing. Table 6-4 Non-PC Performance Test Item and Configuration DIP Switches Recycler Test Item...
  • Page 75: Performance Test Without Pc Procedure

    Performance Tests UBA-RC™ Series Banknote Recycler Section 6 Performance Test without PC Procedure Perform the following steps to execute UBA-RC ™ performance Tests No.2 through No.9 without a 1. Turn the UBA-RC Power Switch to ™ 2. Set the desired DIP Switches on the UBA Trans- ™...
  • Page 76 Section 6 UBA-RC™ Series Banknote Recycler Performance Tests THIS PAGE INTENTIONALLY LEFT BLANK P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 6 - 1 6...
  • Page 77: Exploded Views And Parts Lists

    UBA-RC™ Series Banknote Recycler S e c t i o n 7 7 EXPLODED VIEWS AND PARTS LISTS This section provides product exploded views and • UBA-RC RC Space Unit Exploded View parts lists for UBA-RC Series Banknote Recycler ™ UBA-RC Rear Transport Assembly ...
  • Page 78: Entire Uba-Rc Unit Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists Entire UBA-RC Unit Parts List Table 7-1 UBA-RC Unit Parts List Ref No. EDP No. Description Remark 196488 UBA/iPRO-RC Frame 216287 UBA/iPRO-RC Frame (Large Cash Box) CPU Board Type: 197726 UBA-RC Transport Unit (UBA-12) 16Mbit Flash Rom...
  • Page 79: Uba-Rc Frame Unit 1 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Frame Unit 1 Exploded View Figure 7-2 UBA-RC Frame Unit 1 Exploded View Figure 7-2 UBA-RC Frame Unit 1 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 3...
  • Page 80: Uba-Rc Frame Unit 1 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Frame Unit 1 Parts List Table 7-2 UBA-RC Frame Unit 1 Parts List Ref No. EDP No. Description Remark 265015 RC Bezel Assy. 196443 UBA/iPRO-RC Upper Frame 265780 UBA/iPRO Transport Rail 196441 UBA/iPRO-RC Rear Frame...
  • Page 81: Uba-Rc Frame Unit 2 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Frame Unit 2 Exploded View Figure 7-3 UBA-RC Frame Unit 2 Exploded View Figure 7-3 UBA-RC Frame Unit 2 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 5...
  • Page 82: Uba-Rc Frame Unit 2 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Frame Unit 2 Parts List Table 7-3 UBA-RC Frame Unit 2 Parts List Ref No. EDP No. Description Remark 196440 UBA/iPRO-RC Base Frame 196439 UBA/iPRO-RC Middle Frame 195324 Frame Transport Guide 195323 Pinch Roller Holder...
  • Page 83: Uba-Rc Frame Unit 3 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Frame Unit 3 Exploded View Figure 7-4 UBA-RC Frame Unit 3 Exploded View Figure 7-4 UBA-RC Frame Unit 3 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 7...
  • Page 84: Uba-Rc Frame Unit 3 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Frame Unit 3 Parts List Table 7-4 UBA-RC Frame Unit 3 Parts List Ref No. EDP No. Description Remark 196451 RC Latch Case 196452 RC Latch Button 196472 Latch Button Spring 196453 RC Latch Left...
  • Page 85: Uba-Rc Frame Unit 4 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Frame Unit 4 Exploded View Figure 7-5 UBA-RC Frame Unit 4 Exploded View Figure 7-5 UBA-RC Frame Unit 4 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 9...
  • Page 86: Uba-Rc Frame Unit 4 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Frame Unit 4 Parts List Table 7-5 UBA-RC Frame Unit 4 Parts List Ref No. EDP No. Description Remark 196448 Frame Guide 3 196450 Sensor Cover 196446 Frame Guide 1 102984 Cash Box Holder B 052649...
  • Page 87: Uba-Rc Frame Unit 5 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Frame Unit 5 Exploded View Figure 7-6 UBA-RC Frame Unit 5 Exploded View Figure 7-6 UBA-RC Frame Unit 5 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 1 1...
  • Page 88: Uba-Rc Frame Unit 5 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Frame Unit 5 Parts List Table 7-6 UBA-RC Frame Unit 5 Parts List Ref No. EDP No. Description Remark 196449 Frame Guide 4 196450 Sensor Cover 196447 Frame Guide 2 102983 Cash Box Holder A 052649...
  • Page 89: Uba-Rc Rc Space 1 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC RC Space 1 Exploded View Figure 7-7 UBA-RC RC Space 1 Exploded View Figure 7-7 UBA-RC RC Space 1 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 1 3...
  • Page 90: Uba-Rc Rc Space 1 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC RC Space 1 Parts List Table 7-7 UBA-RC RC Space 1 Parts List Ref No. EDP No. Description Remark 251308 Door 080522 Personal Coin Lock Mini 195897 Tang 196462 Length Guide 120 (Gray) 196464...
  • Page 91: Uba-Rc Rc Space 2 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC RC Space 2 Exploded View Figure 7-8 UBA-RC RC Space 2 Exploded View Figure 7-8 UBA-RC RC Space 2 Exploded View UBA-RC RC Space 2 Parts List Table 7-8 UBA-RC RC Space 2 Parts List Ref No.
  • Page 92: Uba-Rc Rc Space 3 Exploded View

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC RC Space 3 Exploded View Figure 7-9 UBA-RC RC Space 3 Exploded View Figure 7-9 UBA-RC RC Space 3 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 1 6...
  • Page 93: Uba-Rc Rc Space 3 Parts List

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC RC Space 3 Parts List Table 7-9 UBA-RC RC Space 3 Parts List Ref No. EDP No. Description Remark 195894 RC Base 195913 Table 195888 Fulcrum Shaft 195893 RC Middle Base 195887 Rack Drive Shaft...
  • Page 94: Uba-Rc Rc Space 4 Exploded View

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC RC Space 4 Exploded View Figure 7-10 UBA-RC RC Space 4 Exploded View Figure 7-10 UBA-RC RC Space 4 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 1 8...
  • Page 95: Uba-Rc Rc Space 4 Parts List

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC RC Space 4 Parts List Table 7-10 UBA-RC RC Space 4 Parts List Ref No. EDP No. Description Remark 195890 RC Frame Assy Left 195880 Rack Guide Roller 195911 Width Guide Left 195876...
  • Page 96: Uba-Rc Rc Space 5 Exploded View

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC RC Space 5 Exploded View Figure 7-11 UBA-RC RC Space 5 Exploded View Figure 7-11 UBA-RC RC Space 5 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 2 0...
  • Page 97: Uba-Rc Rc Space 5 Parts List

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC RC Space 5 Parts List Table 7-11 UBA-RC RC Space 5 Parts List Ref No. EDP No. Description Remark 1000 195883 RC Flapper Shaft 1001 195905 Flapper Right 1002 195901 Flapper Lever SP...
  • Page 98: Uba-Rc Rear Transport Assembly 1 Exploded View

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Rear Transport Assembly 1 Exploded View Figure 7-12 UBA-RC Rear Transport Assembly 1 Exploded View 1100 1101 1105 1102 1101 1103 1104 1101 1101 1105 1102 1103 Figure 7-12 UBA-RC Rear Transport Assembly 1 Exploded View UBA-RC Rear Transport Assembly 1 Parts List Table 7-12 UBA-RC Rear Transport Assembly 1 Parts List Ref No.
  • Page 99: Uba-Rc Rear Transport Assembly 2 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Rear Transport Assembly 2 Exploded View Figure 7-13 UBA-RC Rear Transport Assembly 2 Exploded View Figure 7-13 UBA-RC Rear Transport Assembly 2 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} ©...
  • Page 100: Uba-Rc Rear Transport Assembly 2 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Rear Transport Assembly 2 Parts List Table 7-13 UBA-RC Rear Transport Assembly 2 Parts List Ref No. EDP No. Description Remark Rear Transport Main Frame Assy. 1 1200 195442 Rear Transport Idler Pulley 2 1201...
  • Page 101: Uba-Rc Rear Transport Assembly 3 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Rear Transport Assembly 3 Exploded View Figure 7-14 UBA-RC Rear Transport Assembly 3 Exploded View Figure 7-14 UBA-RC Rear Transport Assembly 3 Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} ©...
  • Page 102: Uba-Rc Rear Transport Assembly 3 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Rear Transport Assembly 3 Parts List Table 7-14 UBA-RC Rear Transport Assembly 3 Parts List Ref No. EDP No. Description Remark Rear Transport Main Frame Assy. 2 1300 195758 Timing Belt 1301...
  • Page 103: Uba-Rc Rear Transport Assembly 4 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Rear Transport Assembly 4 Exploded View Figure 7-15 UBA-RC Rear Transport Assembly 4 Exploded View 1400 1401 1402 1403 1405 1404 1407 1408 1400 1401 1402 1403 1405 1406 1407 Figure 7-15 UBA-RC Rear Transport Assembly 4 Exploded View...
  • Page 104: Uba-Rc Rear Transport Assembly 4 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Rear Transport Assembly 4 Parts List Table 7-15 UBA-RC Rear Transport Assembly 4 Parts List Ref No. EDP No. Description Remark Rear Transport Main Frame Assy. 3 1400 195929 Rear Transport Shaft 5 1401...
  • Page 105: Uba-Rc Rear Transport Assembly 5 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Rear Transport Assembly 5 Exploded View Figure 7-16 UBA-RC Rear Transport Assembly 5 Exploded View 1500 1507 1508 1509 1503 1511 1510 1505 1501 1502 1506 1504 1505 1506 1507 1504...
  • Page 106: Uba-Rc Rear Transport Assembly 5 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Rear Transport Assembly 5 Parts List Table 7-16 UBA-RC Rear Transport Assembly 5 Parts List Ref No. EDP No. Description Remark Rear Transport Main Frame Assy. 4 1500 005555 M2.6x6 W Washer (Small) 1501...
  • Page 107: Uba-Rc Rear Transport Assembly 6 Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 UBA-RC Rear Transport Assembly 6 Exploded View Figure 7-17 UBA-RC Rear Transport Assembly 6 Exploded View 1602 1601 1600 1607 1608 1607 1610 1609 1608 1606 1610 1604 1605 1603 1604 Figure 7-17 UBA-RC Rear Transport Assembly 6 Exploded View...
  • Page 108: Uba-Rc Rear Transport Assembly 6 Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Rear Transport Assembly 6 Parts List Table 7-17 UBA-RC Rear Transport Assembly 6 Parts List Ref No. EDP No. Description Remark Rear Transport Main Frame Assy. 5 1600 144840 2.6x8 Phillips, Self Tightening, Binding 1601...
  • Page 109: Wba-Sh2 Cash Box Exploded View 1

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 WBA-SH2 Cash Box Exploded View 1 Figure 7-18 WBA-SH2 Cash Box Exploded View 1 1701 1700 1702 Figure 7-18 WBA-SH2 Cash Box Exploded View 1 WBA-SH2 Cash Box Parts List 1 Table 7-18 WBA-SH2 Cash Box Parts List 1 Ref No.
  • Page 110: Wba-Sh2 Cash Box Exploded View 2

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists WBA-SH2 Cash Box Exploded View 2 Figure 7-19 WBA-SH2 Cash Box Exploded View 2 1817 1812 1816 1811 1810 1807 1812 1816 1810 1809 1808 1815 1814 1806 1802 1813 1801 1804...
  • Page 111: Wba-Sh2 Cash Box Parts List 2

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 WBA-SH2 Cash Box Parts List 2 Table 7-19 WBA-SH2 Cash Box Parts List 2 Ref No. EDP No. Description Remark 1800 064391 Handle Plate 1801 064526 Box Handle 1802 064390 Front Box Cover 1803...
  • Page 112: Wba-Sh2 Cash Box Exploded View 3

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists WBA-SH2 Cash Box Exploded View 3 Figure 7-20 WBA-SH2 Cash Box Exploded View 3 1900 1900 Figure 7-20 WBA-SH2 Cash Box Exploded View 3 WBA-SH2 Cash Box Parts List 3 Table 7-20 WBA-SH2 Cash Box Parts List 3 Ref No.
  • Page 113: Wba-Sh2 Cash Box Exploded View 4

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 WBA-SH2 Cash Box Exploded View 4 Figure 7-21 WBA-SH2 Cash Box Exploded View 4 2015 2017 2017 2013 2011 2014 2012 2010 2007 2009 2008 2006 2005 2016 2016 2006 2017 2002...
  • Page 114: Wba-Sh2 Cash Box Parts List 4

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists WBA-SH2 Cash Box Parts List 4 Table 7-21 WBA-SH2 Cash Box Parts List 4 Ref No. EDP No. Description Remark 2000 070740 Pusher Plate 82 2001 081620 O-Ring 2002 052557 Pusher Link 1 2003...
  • Page 115: Wba-Sh2 Cash Box Exploded View 5

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 WBA-SH2 Cash Box Exploded View 5 Figure 7-22 UBA-RC Frame Unit 5 Exploded View Figure 7-22 WBA-SH2 Cash Box Exploded View 5 P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. 7 - 3 9...
  • Page 116: Wba-Sh2 Cash Box Parts List 5

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists WBA-SH2 Cash Box Parts List 5 Table 7-22 WBA-SH2 Cash Box Parts List 5 Ref No. EDP No. Description Remark 2100 064414 SH Pusher Cover 2101 064428 Cover Beam 2102 064524 Arm Spring...
  • Page 117 Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 Table 7-22 WBA-SH2 Cash Box Parts List 5 Ref No. EDP No. Description Remark 2141 052514 Pulley W5 A 2142 064416 Pusher Banknote Guide 2143 064430 Guide Beam 2144 064431 Roller Beam 2145...
  • Page 118: Uba-Rc Large Cash Box Frame Unit Exploded View

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists UBA-RC Large Cash Box Frame Unit Exploded View Figure 7-23 UBA-RC Large Cash Box Frame Unit Exploded View 2202 2205 2200 2204 2205 2201 2204 2205 2205 2203 Figure 7-23 UBA-RC Large Cash Box Frame Unit Exploded View UBA-RC Large Cash Box Frame Unit Parts List Table 7-23 UBA-RC Large Cash Box Frame Unit Parts List Ref No.
  • Page 119: Optional Lock Unit Exploded View

    Exploded Views and Parts Lists UBA-RC™ Series Banknote Recycler Section 7 Optional Lock Unit Exploded View Figure 7-24 UBA-RC Optional Lock Unit Exploded View OP11 OP11 OP10 Figure 7-24 UBA-RC Optional Lock Unit Exploded View P/N 960-100928R_Rev. 3 {EDP #192692} ©...
  • Page 120: Optional Lock Unit Parts List

    Section 7 UBA-RC™ Series Banknote Recycler Exploded Views and Parts Lists Optional Lock Unit Parts List Table 7-24 UBA-RC Optional Lock Unit Parts List Ref No. EDP No. Description Remark 204987 UBA/iPRO-RC Key Bracket 204986 UBA/iPRO-RC Key Lever 204989 Key Unit Block 149984 Key Shaft 149643...
  • Page 121: Index

    UBA-RC™ Series Banknote Recycler S e c t i o n 8 8 INDEX Cleaning methods of, equipment required for ... Recycler Communications acronym for a criteria regarding receipt of ... Safety pictographs indicating Dimensions 1 to 3 symbols inside boxed area entire unit clearance Special Notes illustrated drawing for...
  • Page 122 Section 8 UBA-RC™ Series Banknote Recycler INDEX THIS PAGE INTENTIONALLY LEFT BLANK © 2018, JAPAN CASH MACHINE CO., LTD. P/N 960-100928R_Rev. 3 {EDP #192692} 8 - 2...
  • Page 123: A Troubleshooting

    UBA-RC™ Series Banknote Recycler A p p e n d i x A A TROUBLESHOOTING Troubleshooting Overview This section provides Troubleshooting instructions for the UBA-RC Series Banknote Recycler ™ This product allows the Operator to perform fault ) Unit.  (UBA-10/12-SH2/SS-RC;...
  • Page 124: Table A-2 Rc Unit Led Color Type Error Code Conditions

    Appendix A UBA-RC™ Series Banknote Recycler Troubleshooting Table A-1 UBA Unit LED Code Conditions Green LED Red LED Error Causes ™ Flashes 8 times Communication Error occurred between the UBA Transport Unit and the RC Unit. RC Unit Software download failure. Flashes 9 times Detected abnormal Banknote position during transportation.
  • Page 125: Table A-3 Recycler Unit Led Code Conditions

    Troubleshooting UBA-RC™ Series Banknote Recycler Appendix A Table A-3 and Table A-4 list the two (2) Tri-Color LED Status/Error Code indications for the Recycler Unit Assembly. Table A-3 Recycler Unit LED Code Conditions Left LED Right LED Causes While storing Banknotes, or during an error occurring when Banknotes are being stored.
  • Page 126: Uba-Rc Recycler Unit Width And Length Guide Replacement  Procedure

    Appendix A UBA-RC™ Series Banknote Recycler Troubleshooting UBA-RC Recycler Unit Width and Figure A-2 Length Guide Removal Length Guide Replacement  Procedure The UBA-RC Width and Length Guides located in ™ the Recycler Unit need to be replaced by a trained Engineer or Technician using the following Proce- dures.
  • Page 127: Width Guide Replacement

    Troubleshooting UBA-RC™ Series Banknote Recycler Appendix A Width Guide Replacement 5. Reassemble the RC Race (Figure A-6 a) onto the Recycler Unit. To replace the Width Guide in the Recycler Unit, NOTE: Ensure that no space exists proceed as follows: where the RC Race convex area 1.
  • Page 128: Figure A-7 Additional Maintenance Equipment Requirements

    Appendix A UBA-RC™ Series Banknote Recycler Troubleshooting Maintenance Equipment Requirements Maintenance  This portion provides product information for obtaining the additional UBA-RC ™ Equipment. Additional UBA-RC Maintenance Equipment Figure A-7 Additional Maintenance Equipment Requirements Only the European Connector Version is shown here. Order the “JAC No.”...
  • Page 129: B Glossary

    UBA-RC™ Series Banknote Recycler A p p e n d i x B B GLOSSARY Anti-Pullback Mechanism The rotating drum located in the rear portion of the transport to prevent a Banknote from being retrieved by an attached piece of string, wire or transparent tape ...1-4 Banknote Guide a specific length and width shim designed to center and limit a specific Country’s Banknote size for proper transport through the Validator ...A-5...
  • Page 130 Appendix B UBA-RC™ Series Banknote Recycler Glossary Friction Roller System a Roller assembly designed to separate closely placed Banknotes for entry into the Re- cycler Unit ...1-6 Holographic image a 3-Dimensional image created by using a technique that allows light scattered from an object to be recorded and later reconstructed so that when an imaging system (a Camera, CIS or a Human Eye) is placed in a re-constructed beam of light, an image of the object recorded will be seen even when the object is no longer present.
  • Page 131 Glossary UBA-RC™ Series Banknote Recycler Appendix B 16 RC1 Bin Space/RC2 Bin Space the specific Banknote storage areas in the Recycler portion of an UBA-RC™ Unit ...2-7 17 Recycler The UBA-RC™, an optional add-on device for the UBA™ Banknote Validator. The Re- cycler adds additional capability and functionality to the UBA™...
  • Page 132 Appendix B UBA-RC™ Series Banknote Recycler Glossary THIS PAGE INTENTIONALLY LEFT BLANK P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD. B - 4...
  • Page 133 UBA-RC™ Series Banknote Recycler P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD.
  • Page 134 UBA-RC™ Series Banknote Recycler Issue #4088-SME-01-03 P/N 960-100928R_Rev. 3 {EDP #192692} © 2018, JAPAN CASH MACHINE CO., LTD.

Table of Contents

Save PDF