HA100 Deployment Methods

There are two deployment methods for adding an HA100 and a secondary UCM6510 to an existing
UCM6510 setup:

Method 1: Backup and Restore Configuration

Step 1: Upgrade UCM A to firmware version 1.0.15.13 or higher, and create a full backup
(backup_A).
Step 2: Upgrade UCM B to the same firmware as UCM A, and "backup_A" to UCM B. UCM A and
UCM B should now have same configuration and data.
Step 3: Connect all the cables as described in [UCM6510 and HA100 Connection] section
"HA100 Connection". Make sure all ports A in HA100 are connected to UCM A, and all ports B are
connected to UCM B.
Step 4: Make sure UCM A, UCM B and HA100 are up and running. Access UCM_A's web UI,
enable HA under System SettingsHA.
Step5: Save and apply changes before rebooting.

Method 2: Sync Configuration

Step 1: Upgrade UCM A to firmware version 1.0.15.13 or higher, then make a full backup
(backup_A).
Step 2: Upgrade UCM B to same firmware as UCM A.
Step 3: Setup the connections as described in the [UCM6510 and HA100 Connection], EXCEPT
heartbeat connection between UCM A and UCM B.
Step 4: Access UCM_A's web UI, enable HA under System SettingsHA and reboot UCM A.
Step 5: Establish the heartbeat connection between UCM A and UCM B. UCM A should now sync
its configuration to UCM B.