7 Initial Start-Up

7.1 Procedure

Before you can commission the inverter, you must check various settings and make any necessary
changes. This section describes the procedure for initial start-up and provides an overview of the steps
that must always be performed in the given sequence.
Procedure
1.
Check the country data set configuration of
the inverter.
2.
If the country data set is not correctly
configured for your country or purpose, set it
to the required country data set
3.
Check which configuration of the display
language is set and adjust as necessary.
4.
Carry out initial commissioning of the inverter
and start self-test, if required.

7.2 Changing the Country Data Set

The inverter is set by default to a specific country data set. You can find the country data set configured
on the inverter in the enclosed supplementary sheet with the default settings. If the configured country
data set does not apply to your country, you will need to change the country data set via a
communication product.
Country data set must be correctly configured
If you configure a country data set that is not valid for your country or particular application,
this may cause a plant a disturbance and lead to problems with the network operator.
When selecting the country data set, always observe the locally applicable standards and
directives, as well as the specific plant properties (e.g. plant size, grid-connection point, etc.).
• If you are not sure which country data set is applicable for your country or application,
contact your network operator to clarify the appropriate country data set.
Installation Manual
see supplementary sheet with default
settings
Type label or display
(see Section 7.2 "Changing the Country
Data Set", page 37)
(see Section 7.3 "Changing the Display
Language", page 38)
(see Section 7.4 "Commissioning the
Inverter", page 39)
and if applicable
(see Section 7.5 "For Italy Only: Starting the
Self-test", page 40)
SB13_21TL-IA-en-65
7  Initial Start-Up
37

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sunny boy 1300tlSunny boy 2100tl

Table of Contents