TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL TABLE OF CONTENTS: EXPLANATION OF SYMBOLS AND SAFETY INSTRUCTIONS 1.1. Explanation of symbols 1.2. Requirements to boiler installation room 1.2.1. Instructions to boiler installer 1.2.2. Instructions to installation user 1.2.3. Minimum clearances for installation and combustibility of building materials PRODUCT DESCRIPTION FUELS...
• Regulations and norms concerning the fitting of the heating installation with safety devices. • It is necessary to install a smoke detector in the boiler room. Use only original BURNiT parts ! 2 -EN...
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL DANGER of fire when burning flammable materials or liquids. - Flammable materials/liquids must not be left in close proximity of the heating boiler. - Indicate to the user of the installation the valid minimum distances to flammable materials.
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL Safety rules for user operation: - Operate the heating boiler at a maximum temperature of 85°C, and to that end you must regularly inspect the boiler room. - Do not use flammable liquids for ignition or increase the fire or increase boiler’s output.
• Versatile. It is designed for burning solid fuels. The boiler has an option to adapt to other fuel sources: by mounting a pellet burner BURNIT PELL 150kW or PELL MEGA 300kW respectively to WBS Magna 160kW or WBS Magna 250kW. The mounting is performed by a specially designed opening on the lower door with the help of special mounting kit.
When transporting items weighing more than 30 kg, the use of pallet jack, fork truck or other hoisting devices is a must. Large sized boilers BURNiT WBS Magna 160kW and 250 kW require transportation to be carried out using a forklift. For this purpose at the lower part of the boiler are provided transportation holes.
Page 8
WBS Magna A, mm B, mm C, mm D, mm Weight, kg 250 kW 1000 2120 2310 1585 160 kW 1900 1980 1210 Diagram 3. Overall dimension of boiler body and housing, model WBS Magna 160kW and 250kW 7 -EN...
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 5. DELIVERY OF THE BOILER • Inspect the integrity of the packaging upon delivery. • Check whether all components have been delivered to you. Boiler scope of delivery includes: 1) Boiler body with boiler doors. 2) Safety valve 4 bar.
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL - No objects made of flammable materials or liquids may be placed on/near the boiler; 6.2. Assembly / disassembly of the boiler housing Diagram 4. Elements of boiler housing, model WBS Magna 160kW and 250kW Table 3 № Element...
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL Steps to assemble the panels of the boiler housing: Step 1: Fix Lower side panel 1 to boiler body by using Auxilliary mounting plate 12 Step 2: Fix Side middle panel 2 to boiler body by using Auxilliary mounting plate 12 Step 3: Mount thermometer - place the probe into sensor sleeve Fix Upper right side panel 3 to boiler body by using Auxilliary mounting...
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 7. SETUP OF THE HEATING BOILER 7.1. Connecting the boiler to a chimney Boiler-to-chimney connection must always comply with the existing standards and rules. The chimney must provide sufficient draught for evacuation of the smoke under any conditions.
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL The inner diameter of the chimney depends on its real height and the power capacity of the boiler (see diagram 5). Please entrust choosing a chimney and its installation by a qualified professional. The required distance between the boiler and the chimney is 300 - 600 mm.
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 7.3. Connecting the boiler to the heating installation. Such connection must be performed by a technician / service shop authorized for such operations. When the boiler is connected to a heating system, it is mandatory to install a 4 bar relief valve and expansion vessel.
Page 15
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL Output too low 1. Insufficient draught. Check chimney condition measure draught. (must be performed by an authorized service) 2. The heating capacity of the fuel is too 2. Make sure you are using dry fuel. low (not sufficicent).
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 7.4. Connection diagrams 7.4.1. Connection of BURNiT WBS Magna boiler in a closed system Such connections must be performed by a technician / service shop authorized for such operations. Diagram 7 1 - Thermostat...
Page 17
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 7.4.2. Connection of BURNiT WBS Magna boiler in an open system Diagram 8 1 - Cold water inlet 5 - Return valve 2 - Drainage 6 - Insulation 3 - Air vent line 7 - Hot water outlet...
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 8. FILLING THE HEATING INSTALLATION Table 5 Problem Prevention Possible installation damage due to Fill the heating installation only in cold strains in the material caused by conditions (inlet temperature must not temperature differences. exceed 40°C).
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 9.2. Adjust the boiler combustion by thermostatic draft regulator Adjusting. Heat the boiler up to 80°С. Control valve is placed in a position to meet the temperature reading on the thermometer. Red numbers and red indicator point are valid for vertical mounting.
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL Tar deposits or residues of non- combustive materials inside the boiler firebox deteriorate normal combustion process. 4. Clean up to the end fume exhaust tube with the brush. Blockage interfere with normal operation of the boiler and reduces power. 5.
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 10. WARRANTY TERMS The warranty terms are described in the Service booklet included in the supply. 11. TECHNICAL PARAMETERS 11.1. General features: - The maximum operating pressure is 4 bar - enough to feed a large-scale heating system.
Page 22
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL Diagram 9. Elements of WBS Magna 160kW /250kW 1. Hot water uotlet; 9. Transportation openings; 2. Safety line sleeve; 10. Air intake door; 3. Thermal wool insulation; 11. Opening for mounting a burner with protective cover 4.
Page 23
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 11.2. Technical parameters Table 6. Model WBS MAGNA 160kW 250kW Heat output m² 1200÷1600 2000÷2500 Heating surface 1800 2150 Height H 850/1880 950/2070 Width L/ Depth D Mantle volume Combustion chamber volume Pa/mbar 23/0.23 23/0.23 Combustion chamber resistance Pa/mbar...
Page 24
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL Max.lenght of firewood logs 4.5/3.0 5.5/3.5 Burning time partial/full load Operating temperature range / °C 65÷85 /95 Max. temperature Exhaust gas temperature °C 120÷150 150÷180 (operation mode) Operating pressure 1100 1550 without insulation Weight with insulation 1170 1630...
TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 12. RECYCLING AND WASTE DISPOSAL 12.1 Recycling of boiler packaging Parts of the packaging made of wood or paper can be used as combustible. Submit the rest of the packaging material for recycling according to the local regulations and requirements.