Unpacking and Inspection

Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You should
have received the following items inside of package:
 The unit x 1
 User manual x 1
 RJ45 cable x 1
 RS-232 cable x 1

Preparation

Before connecting all wirings, please take off bottom cover by removing two screws as shown below.

Mounting the Unit

Consider the following points before selecting where to install:
Do not mount the inverter on flammable construction
materials.
Mount on a solid metal surface.
Avoid direct sunlight. Be sure the environment is shady and
cool.
Be sure to install the inverter into a box with waterproof and
dustproof.
Install this inverter at eye level in order to allow the LCD
display to be read at all times.
The recommended installation position is to be adhered to
the wall vertically.
Be sure to keep other objects and surfaces as shown in the
diagram to guarantee sufficient heat dissipation and to
have enough space for removing wires.
SUITABLE FOR MOUNTING ON CONCRETE OR
OTHER NON-COMBUSTIBLE SURFACE ONLY.