5.3

Powering Up ROME

Once the ROME Chassis and LCU have been installed, connected through signaling cables, and properly
grounded, the ROME equipment can be powered up.
The power cable connections are located on the front panel of the LCU.
For the AC unit, use an approved power cord with IEC 60320 C13 plug. For the DC unit, use the Molex Female
Connector part number 394250002 to connect the DC wiring.
The LCU front panel has three LEDs. These LEDs provide a quick visual indication of the system's
functional status.
Connect power to the LCU front panel power supply. After power is connected to the first power supply, the
ROME chassis will automatically start up and go through an initial set up.
Once ROME has successfully powered on, all three LEDs will begin blinking. The hardware installation is now
complete. The next step is to configure the ROME software and ROME users, which is covered in the ROME
Administrator's Manual.
Note: For systems that have already been configured and loaded with software from the factory, the system
will switch to operational mode immediately after power up and initialization.
Note: The LCU LEDs will continue blinking until the device switches to operational mode once the ROME
software is configured.
Page 16
www.wave-2-wave.com
Hardware
Installation Manual
DOC-0001

Hide quick links:

Advertisement

Table of Contents
loading

Related Products for Wave2wave Rome500

Table of Contents