General
Any installation work MUST be carried out by suitably qualified personnel.
considerations
The following considerations should be taken into account before deciding on the
location for the SKE-XL Steam Humidifier:
!
Positioning the
Humidifier
Minimum
Minimum clearances are :
Clearances
The humidifier is designed to be installed directly on the floor.
Provide a level, solid foundation for the humidifier.
Ensure that the floor beneath the humidifier is water proof to withstand any water
spillage during servicing or if a problem occurs.
The humidifier is provided with adjustable legs in order to ensure proper level.
Stage 1 – Unit Positioning and Mounting
Plan a location easy to access in order to permit an easy inspection and
servicing of the humidifier.
Do not install humidifier where failure of the appliance could cause damage
to the building structure or to costly equipment.
Location area should be well ventilated, ambient temperature should not
exceed 30˚C.
The humidifier must be installed to ensure the steam hose length is kept to the
shortest possible length.
For flexible steam hose: the total steam line length should not exceed 5
meters. For longer distances use insulated hard piping.
For insulated hard piping: the total steam line length should not exceed 15
meters. For longer steam line runs, consult factory.
Observe the minimum access distances as shown in Illustration 5.
510 mm
minimum
(Illus. 5) Standard enclosure
 Top: 510mm minimum
 Electrical panel side: 600mm minimum
 Front: 800mm minimum
SKE-XL Steam Humidifier
Installation Instructions and User Manual
9

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ske120Ske-xlSke100Ske110Ske-xl series

Table of Contents