Beluk BLR-CM Commissioning Instructions

Power factor regulator
Hide thumbs Also See for BLR-CM:

Advertisement

Quick Links

Commissioning Instructions
Power Factor regulator BLR-CM
the device check that all connecting leads are de-
energized and that current transformers are bypassed.
1)
Compare auxiliary-, measurement-, control voltage, fre-
quency and the current path of the device (see type label)
with the data of the electricity network.
2)
Assemble the relay in the switch panel with the 2 mounting
clips. If the device is not fitting in the cutout the small plas-
tic bars on the side of the case can be removed with a
knife.
3)
Connect protective ground to the terminal link of the case.
4)
Connect in accordance to the wiring diagram. Pay special
Attention to the cross section size of the CT connections!
An integrated voltage observation with regard to the auxil-
iary voltage in BLR-CM guarantees a safety disconnection
of the capacitors in case of undervoltage. It must be en-
sured, that auxiliary voltage is taken from the identical
phase as control voltage for the contactors, to guarantee
that all switching elements are safely switched off in case of under voltage.
5)
Remove short circuit links of the current transformer before commissioning!

Display

User Interface of BLR-CM is a graphical LCD and a membrane keyboard with 4 softkeys.
LCD is split into 4 areas:
:
Status columns
left and right column are showing the status of the control exits.
1
Step 1, status: off, type: NORMAL
2!
Step 2, status: off, type: NORMAL blocked or FIX OFF
F
Step 3, status: off, type: FAULTY
4
Step 4, status: on, type: NORMAL
5!
Step 5, status: on, type: FIX ON
Step 6, status: off, type: OFF, not available or PFC OFF
"NORMAL blocked" can be caused by discharging time
"PFC OFF" can be caused by voltage out of tolerance, by relay is off due to setting or due to Alarm system.
Main area:
the three lines of main area are for menu navigation and display of information
Softkey area:
the soft key area shows the function of the membrane-keyboard. Depending on the opened menu, the function
is different.

Connection

Only qualified staff is
allowed to perform the
installation. All legal
rules have to be ob-
served and technical
standards have to be
met. Before connecting
Top area:
The two lines of top area are showing information about general status of the relay. The readings of this
area are always available, independent from the menu which is used. The readings of top area can be
parametered in menu SETUP/DISPLAY.
The "sad face" indicates that there are problems with the level of voltage or current.
The "happy face" indicates that levels of voltage and current are ok.
The "serious face" indicates setting PFC OFF or PFC FREEZE.
Einspeisung
Supply
L1
L2
L3
BLR-CM
N
PE
Einspeisung
Supply
L1
L2
L3
BLR-CM
N
PE
Rev. 03
Last
Load
K1
K1
Last
Load
K1
K1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the BLR-CM and is the answer not in the manual?

Questions and answers

Summary of Contents for Beluk BLR-CM

  • Page 1 Remove short circuit links of the current transformer before commissioning! Display User Interface of BLR-CM is a graphical LCD and a membrane keyboard with 4 softkeys. LCD is split into 4 areas: Top area: The two lines of top area are showing information about general status of the relay.
  • Page 2 For ease of use and adjustment the BLR-CM user interface consists of a combination of graphical LCD display and 4 soft-press-keys. The following flow chart shows step by step how to commission the BLR-CM. The steps below should be followed by pressing the high- lighted soft-press-keys on the BLR-CM.
  • Page 3 Commissioning Instructions Rev. 03 Power Factor regulator BLR-CM Page 3 of 4 STEP TYPE: STEP 01 Following step types are possible: STEPS STEP TYPE NORMAL NORMAL = step is used for normal regulation        ...
  • Page 4 Commissioning Instructions Rev. 03 Power Factor regulator BLR-CM Page 4 of 4 Harmonics for current and voltage up to 31st order MEAS: VALUES > HARMONICS < STEPINFO Display Step type, switching operations, Step size. HARMONICS > STEPINFO < SETUP Factory setting Adjustable range CHANGE LANG.

Table of Contents