Maintenance - Danfoss Termix One Solar Operating Manual

Table of Contents

Advertisement

Operating guide
6.1.3 Domestic hot water pump
The domestic hot water pump can be programmed with the
desired time programme.

6.2 Maintenance

The substation requires little monitoring, apart from routine
checks. It is recommended to read the energy meter at regular
intervals, and to write down the meter readings.
Regular inspections of the substation according to this Instruction
are recommended, which should include:
Strainers
Cleaning of strainers.
Meters
Checking of all operating parameters such as meter readings.
Temperatures
Checking of all temperatures, such as DH supply temperature and
DHW temperature.
Connections
Checking all connections for leakages.
Safety valves
The operation of the safety valves should be checked by turning
the valve head in the indicated direction.
Venting
Checking that the system is thoroughly vented.
Inspections should be carried out minimum every two years.
Spare parts can be ordered from Danfoss. Please ensure that any
enquiry includes the substation serial number.
Danfoss District Energy
Termix One Solar
VI.CW.K4.02 / LUK38004
Authorized personnel only
Assembly, start-up and maintenance work must be performed by
qualified and authorized personnel only.
DEN-GT