MEZZO FIBRE CEMENT SHEETING
TIMBER FRAME
IMPORTANT:
• Wall lining is to be fixed to timber frame only
• At no point is the wall lining to be screwed or
• The unit must be able to expand and contract
• Unit and heat board is to finish flush with front
• If the fibre cement sheeting is to be fixed to the
23/03/2017
INSTALLATION INSTRUCTION
glued to the unit.
independently to the frame and wall lining,
otherwise cracking will occur.
of timber frame so that 9mm wall lining can be
correctly finished
heat board, Selleys 401 silicone must be used
to allow for expansion.
MEZZO HEAT BOARD TO SIT
FLUSH WITH TIMBER FRAME
Ver.1
ONE PIECE 9mm FIBRE
CEMENT SHEETING
CEMENT SHEETING JOINT TO BE
NEAR BOTTOM OF UNIT WHERE IT WILL
BE COOLER
9mm FIBRE CEMENT SHEETING