Check-Out Procedures

NOTE: Refer to outdoor unit installation instructions for
system start-up instructions and refrigerant charging
instructions.
Pre-Start-Up Checks
Is the air handler properly and securely installed?
If horizontally configured, is the unit sloped up to 5/8
inch toward drain lines?
Will the unit be accessible for servicing?
Has an auxiliary pan been provided under the unit
with separate drain for units installed above a finished
ceiling or in any installation where condensate overflow
could cause damage?
Have ALL unused drain pan ports been properly
plugged?
Has the condensate line been properly sized, run,
trapped, pitched, and tested?
Is the duct system correctly sized, run, sealed, and
insulated?
Have all cabinet openings and wiring been sealed?
Is the indoor coil metering device properly sized for the
outdoor unit being used?
Have all unused parts and packaging been disposed
of properly?
Is the filter clean, in place, and of adequate size?
Is the wiring neat, correct, and in accordance with the
wiring diagram?
Is the unit properly grounded and protected (fused)?
Is the thermostat correctly wired and in a good
location?
Are all access panels in place and secure?
Check Blower Operation
Set thermostat to FAN ON.
The indoor blower should come on.
Check Cooling Operation
Set thermostat to force a call for cooling (approximately
5ºF lower than the indoor ambient temperature).
The outdoor and indoor units should come on
immediately.
Check the air flow from a register to confirm that the
system is moving cooled air.
Set the thermostat 5ºF higher than the indoor
temperature. The indoor blower and outdoor unit
should cycle off. Air handler should cycle off 45
seconds after the outdoor unit shuts off.
507621-01
Check Electric Heater (if used)
Set thermostat to call for auxiliary heat (approximately
5°F above ambient temperature). The indoor blower
and auxiliary heat should come on together. Allow a
minimum of 3 minutes for all sequencers to cycle on.
Set the thermostat so that it does not call for heat.
Allow up to 5 minutes for all sequencers to cycle off.

Operation

Time Delay Relay
Blower time delay operation:
1.
When cooling demand is initiated, there is a 1 second
motor-on delay.
2.
After the motor-on delay expires, motor ramps up
to 100% and runs at 100% until cooling demand is
satisfied.
3.
Once demand is met, motor runs at 100% for 45
seconds.
4.
Motor ramps down to stop.
2
1
1
SECOND
COOLING
DELAY
DEMAND
Cooling (Cooling Only or Heat Pump)
When the thermostat calls for cooling, 24 volts is put on
the blower time-delay relay coil and then the indoor blower
relay energizes. The normally open contacts close, causing
the indoor blower motor to operate. The circuit between R
and Y is completed, closing the circuit to the contactor in
the outdoor unit, starting the compressor and outdoor fan
motor.
On heat pumps, circuit R and O energizes the reversing
valve, switching the valve to the cooling position. (The
reversing valve remains energized as long as the
thermostat selector switch is in the COOL position.)
At the completion of the cooling demand, the indoor blower
and outdoor unit should cycle off. Air handler should cycle
off 45 seconds after the outdoor unit shuts off.
Heating (Electric Heat Only)
When the thermostat calls for heat, the circuit between R
and W is completed, and the heat sequencer is energized.
A time delay follows before the heating elements and the
indoor blower motor come on. Units with a second heat
sequencer can be connected with the first sequencer to W
on the thermostat sub-base, or they may also be connected
to a second stage on the sub-base.
Issue 1720
3
4
100%
100%
CFM
CFM
45
SECS
Figure 21
OFF
Page 19 of 23