For cooling operation under low ambient temperature or any
other operation under low pressure, apply silicon pad or similar
to prevent freezing of the gas stop valve flare nut (see figure).
Freezing of the flare nut may cause refrigerant leak.

9.3. How to use the stop valve

Use hexagonal wrenches 4 mm and 6 mm.
Opening the valve
1.
Place the hex wrench on the valve bar and turn counter-
clockwise.
2.
Stop when the valve bar no longer turns. It is now open.
Closing the valve
1.
Place the hex wrench on the valve bar and turn clockwise.
2.
Stop when the valve bar no longer turns. It is now closed.
Closing direction
Liquid side

9.4. Cautions for handling the valve cover

The valve cover is sealed where
indicated by the arrow.
Take care not to damage it.
After operating the valve, be sure to tighten the valve cover
properly.
Liquid pipe
Gas pipe
Check for refrigerant leakage after tightening the cap.

9.5. Cautions for handling service port

After the work, tighten the valve cover in place.
Tightening torque: 11.5~13.9 N•m
9.6. Precautions when connecting field piping and
regarding insulation
Be careful not to let the indoor and outdoor branch piping come
into contact with the compressor terminal cover.
If the liquid-side piping insulation might come into contact with it,
adjust the height as shown in the figure below. Also, make sure
the field piping does not touch the bolts or outer panels of the
compressor.
When the outdoor unit is installed above the indoor unit the
following can occur:
The condensated water on the stop valve can move to the
indoor unit. To avoid this, please cover the stop valve with
sealing material.
If the temperature is higher than 30°C and the humidity is higher
than RH 80%, then the thickness of the sealing materials should
be at least 20 mm in order to avoid condensation on the surface
of the sealing.
Installation manual
8
Silicon sealing pad
(Make sure there is no gap)
Gas side
Tightening torque
13.5~16.5 N•m
22.5~27.5 N•m
Be sure to insulate the liquid and gas-side field piping and the
refrigerant branch kit.
Any exposed piping may cause condensation or burns
if touched.
(The highest temperature that the gas-side piping can reach is
around 120°C, so be sure to use insulating material which is
very resistant.)
1
2
3
4
1
Compressor
2
Terminal cover
3
Indoor and outdoor
4
field piping
4
Corking, etc.
5
5
Insulation material
(field supply)
5
6
Bolts
6
A
Be careful with pipe,
bolt and outer panel
connections
A
U-4~6ML5DPQ + U-4~6ML5XPQ
Urban Multi air conditioner
4PW40731-1

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

U-5ml5xpqU-4ml5dpqU-6ml5xpqU-6ml5dpqU-4ml5xpq

Table of Contents