LA36 OPERATOR INSTALLATION GUIDE
LA36 OPERATOR INSTALLATION GUIDE
LA36 OPERATOR INSTALLATION GUIDE
LA36 OPERATOR INSTALLATION GUIDE
LA36 OPERATOR INSTALLATION GUIDE
For dual-leaf applications, both linear drive motors will connect to a single control box. Locate the control box in the vicinity of
either linear actuator motor. Mount the box firmly to a non-movable object. Knockouts are provided for conduits. Do not mount
the control box where a lawn sprinkler may spray water on it.
NOTE: When installing the cable connecting the operator to the control box, be sure to leave some slack to allow for the swing
of the gate. Water tight connectors are highly recommended.
Several brackets have been supplied for post or pillar mounting. The post pillar bracket, operator mounting bracket, and spacer
plate can be combined in various configurations to fit most applications. It is very important to achieve the required mounting
location for proper operation and to avoid premature failure.
1. Locate the post pillar bracket vertically approximately halfway up from the ground relative to the overall gate height.
2. If mounting to a round post of 4" diameter or less, use two U-bolts to attach the post/pillar bracket.
3. If mounting to a square post, use either through bolts or, if applicable, weld the bracket to the post directly. Avoid drilling into
mortar joints wherever possible.
4. When mounting to a pillar, anchor the bracket using 1/2" lag bolts and lag bolt anchors. Drill 3/4" diameter holes to a depth
of 4" using a rotary hammer percussion drill. Insert lag bolt anchors for 1/2" diameter lag bolts. Lubricate bolts before
installation and tighten in place when done.
Refer to the illustration on the following page.
1. Open the gate to approximately 90 to 95 degrees (full open position).
2. Carefully mount the operator to the post/pillar bracket assembly and hold the front end of the operator level and in its fully
open position. If necessary, you can temporarily apply power to the operator to open it fully. DO NOT ALLOW THE DRIVE
TUBE TO SPIN!
3. Line up the gate bracket with the linear actuator and mark the position. Clamp the bracket in place. Once its final position
is set, permanently attach the bracket.
4. Run the operator to the fully-closed position, adjusting the close limit as needed to achieve full travel. Make any mounting
changes needed to achieve full travel without the operator binding against the post, gate, etc.
The factory suggested mounting will use approximately 14" of stroke. The maximum available stroke for the LA36 is 18".
A SEPARATE PEDESTRIAN GATE IS REQUIRED FOR ALL PEDESTRIAN TRAFFIC. THIS GATE
MUST BE A MINIMUM DISTANCE OF 7 FEET FROM THE VEHICULAR GATE AND GATE OPERATOR

CONTROL BOX MOUNTING

CONTROL BOX MOUNTING
CONTROL BOX MOUNTING
CONTROL BOX MOUNTING
CONTROL BOX MOUNTING

POST/PILLAR BRACKET INSTALLATION

POST/PILLAR BRACKET INSTALLATION
POST/PILLAR BRACKET INSTALLATION
POST/PILLAR BRACKET INSTALLATION
POST/PILLAR BRACKET INSTALLATION

GATE BRACKET INSTALLATION

GATE BRACKET INSTALLATION
GATE BRACKET INSTALLATION
GATE BRACKET INSTALLATION
GATE BRACKET INSTALLATION
- 5 -
- 5 -
- 5 -
- 5 -
- 5 -
10-05-12

Advertisement

Table of Contents
loading

Table of Contents