Removing The Blade Cover; Installing The Blade Cover; Installing The Feed Chute Ato; Installing The Ejection Chute Extension - Viking GB 460 C Instruction Manual

Garden shredder
Hide thumbs Also See for GB 460 C:
Table of Contents

Advertisement

Available languages
  • EN

Available languages

  • ENGLISH, page 49
Attaching the right wheel carrier:
● Position right wheel carrier (B) on the
inside of angled support plate (1). The
bores in the wheel carrier must align
with the bores in the support plate.
● Position a nut (J) on the inside. Insert
screw (I) through the bores (2) in the
support plate and in the wheel carrier
and screw into the nut (J) but do not
tighten.
● Repeat this procedure at the second
bore in the right wheel carrier.
Attaching the left wheel carrier:
● Hold the left wheel carrier (C) with the
bore (1) at the centre bore (2) on the left
side of the basic unit (A).
● Screw in the screw (I) using the
installation tool (T), but do not tighten.
2 Install the foot and plug:
● Push the foot (D) as far as possible
onto right wheel carrier (1) as shown.
The foot engages in the right wheel
carrier.
● Repeat this procedure on the left wheel
carrier.
Risk of injury:
After installing, check that both feet
are seated securely.
● Carefully drive plug (E) into right wheel
carrier (2) as far as possible.
● Repeat this procedure on the left wheel
carrier.
3 Mount the wheel on the axle:
Mount the wheels so that the valves
are located on the outside.
● Push the retaining ring (G) as far as
possible into the groove (1) in axle (H).
56
● Push the wheel (F) onto the axle (H).
In order to prevent the wheel from
becoming loose when installing,
ensure that retaining ring (G)
engages correctly in the groove (1)
in axle (H).
4 Install the axle and wheel:
● Push the axle, with pre-installed
wheel (1) through the bores (2) in the
wheel carrier.
● Push the left wheel (F) onto the
axle (1).
● Push the retaining ring (G) as far as
possible into the groove in the axle (3).
● Remove the basic unit from the
cardboard insert.
● Raise the basic unit into the working
position.

7.3 Removing the blade cover

● Hold the blade cover (1) at the
bore and lift off the cover.

7.4 Installing the blade cover

● Insert the blade cover (1) under
the counter-blade (2).
Then press down the blade cover (1).
When properly installed, the blade
cover (1) must lie against the blade disc
correctly.
7.5 Installing the feed chute
ATO 400
● Remove the blade cover. (
● Insert the two fastening hooks (1) on
feed chute ATO 400 (K) into the two
openings in the basic unit (2).
● Tilt the feed chute ATO 400 (K)
forwards to the stop.
● Screw in the On / Off switch (3) and
tighten.
Following assembly, check that the
feed chute ATO 400 is correctly
engaged in both openings in the
basic unit.
7.6 Installing the ejection chute
extension
● Carefully set the machine on its
back.
Place cardboard underneath in
order to prevent damage.

Installing the ejection chute extension

● Attach the ejection chute extension (L),
engage the hooks (1) in the apertures
5
on the housing (2) from above, turn
downwards and push on the
retainers (3) at the side.
● Screw in the screws (O) and tighten to
1 - 2 Nm.
6
In order to facilitate installation of
the guiding plate, we recommend
loosening the left wheel carrier
slightly.
● Loosen the screw (4) at the left wheel
carrier by approx. 5 turns.
7
7.3)
8
0478 216 9905 D - EN

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gb 460

Table of Contents