Verifying Contents After Unpacking

Power cables, manuals, and other additional items are packaged in separate boxes. After you have unpacked the system, verify
that you have received all the required components and documentation.
Step 1
Using the packing list as a guide, verify that you have received everything that is listed, including the following:
a. System hardware documentation and software documentation (if ordered).
b. Optional equipment that you ordered, such as transceivers (GBICs), flash cards, cables, or special connectors.
Step 2
Check that all equipment you ordered is installed in the chassis.
Step 3
Ensure that the system configuration matches the packing list.

Attaching the Rack-Mount Brackets

Before installing the chassis in the rack, you must install rack-mount brackets on each side of the front, middle, or rear of the
chassis. If you are rack-mounting the chassis from the front, you cannot use the cable-management bracket. If you are
rack-mounting the chassis at the rear or middle of the chassis, both rack-mount brackets and the cable-management bracket
must be installed on the chassis before the chassis is installed in the rack.
Figure 3
Rack-Mount Bracket Options
1
Rack-mount
bracket
2
Rack-mount bracket
1
Installed in 4-post rack—rear installation
2
Installed in 4-post rack—flush front installation
8
3
Rack-mount
bracket
4
Rack-mount bracket
3
Installed in 4-post rack—protruding front installation
4
Installed in open or relay-type tack