Installing Cables
● Requirements for Laying Out Cables
● Requirements for laying out power cables
1. The power cable must be separated from ground cables and signal cables.
2. If multiple power cables are installed, you must bind the power cables.
3. The routing of power cables must meet engineering design drawing requirements.
4. If the power cable length is insufficient, replace the power cable. The power cable must be complete and cannot
have splices or welding points.
● Requirements for laying out ground cables
1. All ground cables must be connected to a ground bar.
2. The ground cable cannot be led in aerially, but buried in the earth or arranged indoor.
3. Both ends of the external conductor of the coaxial cable and those of the insulation of the shielded cable should
have good electric contact with the metal shell of the equipment they connect to.
4. Ground cables must be separated from signal cables to reduce interference between them.
5. Do not add any switch or fuse on the ground cable.
6. Do not use another device for an electrical connection with the ground cable.
7. All metal components in the shell must be securely connected to the ground cable.
● Requirements for laying out optical fibers
1. Do not press optical fibers forcibly or crush optical fibers with force. Leave sharp objects away from optical fibers
to prevent damage to optical fibers.
2. Coil up redundant optical fibers round specialize devices such as the splice tray.
3. Coil optical fibers gently and do not break them.
4. Cover optical fiber connectors with protective caps.