Checking The Expansion Vessel And System Pressure - Viessmann VITOPLEX 100 Service Instructions Manual

Oil/gas boiler
Table of Contents

Advertisement

Commissioning, inspection, maintenance
Further details regarding the individual steps

Checking the expansion vessel and system pressure

Documentation of the expansion
vessel manufacturer
Expansion vessel
1. Drain the system until the pressure
gauge indicates "0" or close the cap
valve on the expansion vessel and
reduce the pressure in the expansion
vessel.
Note
The pre-charge pressure of the
expansion vessel (p
the static system pressure (p
(= static head) and a supplement
(p
= p
+ supplement).
0
St
The supplement is subject to the set-
tings of the high limit safety cut-out.
For a high limit safety cut-out setting
of
■ 100 °C: 0.2 bar (0.02 MPa)
■ 110 °C: 0.7 bar (0.07 MPa).
For water quality requirements, see page 22.
*1
14
) is made up of
0
)
St
Note
Carry out this test on a cold system.
2. If the pre-charge pressure of the
expansion vessel is lower than the
static system pressure, top up with
nitrogen until the pre-charge pres-
sure is 0.1 to 0.2 bar (0.01 to
0.02 MPa) higher.
The static pressure corresponds to
the static head.
3. Top up softened water
charge pressure of the cooled system
is 0.1 to 0.2 bar (0.01 to 0.02 MPa)
higher than the pre-charge pressure
of the expansion vessel.
Permiss. operating pressure: 5 bar
(0.5 MPa)
(cont.)