Check and test operation
Check
f Be sure to check the following again after completion of installation.
f
1. Check the piping connection area for any gas leakage.
Indoor connection area
2. Is the drain hose properly connected?
3. Is the insulation of the piping in good condition?
4. Is grounding properly made?
Mirage_AP30M0@_IBIM_E_34518A(1).indd 51
Outdoor connection area
Pipe insulator (Over 7mm foamed
polyethylene or EPDM foam)
Pipie connection part insulator (Over 5mm
foamed polyethylene)
More than 30cm
51