Commissioning the tumble dryer
10
– 2. Start a cool air program
To complete the commissioning process, a program cycle
using cool air (Cool air or Timed drying cool air) needs to be
started.
If the power to the tumble dryer is switched off before the
first program is started (e.g. by pressing the K button), the
commissioning process can be repeated. The
commissioning process is only completed once the first
program cycle (at least 20 minutes) has finished.
^ Select a cool air program and confirm your selection.
The menu for the cool air program appears.
^ Press the flashing Start button.
After this program has finished, the tumble dryer is ready for
use.