VI. Venting
A.
Install vent system in accordance with local building
codes; or local authority having jurisdiction; or
National Fuel Gas Code, ANSI Z223.1/NFPA 54, Part
7, Venting of Equipment. Install any of the following
for this Series 16H Category I, draft hood equipped
appliance:
1. Type B or Type L gas vent. Install in accordance
with listing and manufacturer's instructions.
2. Masonry or metal chimney. Build and install in
accordance with local building codes; or local
authority having jurisdiction; or Standard for
Chimneys, Fireplaces, Vents, and Solid Fuel
Burning Appliances.
Masonry chimney must be lined with approved
clay flue lining or listed chimney lining system
except as provided in ANSI Z223.1/NFPA 54,
Paragraph 7.5.4(a): Exception: Where permitted by
the authority having jurisdiction, existing chimneys
shall be permitted to have their use continued when
an appliance is replaced by an appliance of similar
type, input rating, and efficiency.
3. Single wall metal vent. Allowed by ANSI Z223.1/
NFPA 54 under very restrictive conditions.
B.
Inspect chimney and remove any obstructions or
restrictions. Clean chimney if previously used for solid
or liquid fuel-burning appliances or fireplaces.
DANGER
Inspect existing chimney before installing boiler.
Failure to clean or replace perforated pipe or tile
lining will cause severe injury or death.
C.
Install Draft Hood on canopy outlet. Maintain height
from Jacket Top Panel to Draft Hood skirt as shown
in Figure 1. DO NOT ALTER, CUT, OR MODIFY
DRAFT HOOD.
WARNING
Do not alter boiler draft hood or place any
obstruction or non-approved damper in the
breeching or vent system. Flue gas spillage can
occur. Unsafe boiler operation will occur.
D.
Install Blocked Vent Switch. The Blocked Vent
Switch Assembly consists of a strain relief bushing,
power cord, and switch attached to mounting bracket.
The assembly is located in Combination Boiler Parts
and Control Carton.
1. Uncoil power cord.
2. Position mounting bracket onto lower edge of Draft
Hood skirt. Locate center tooth (with #10 sheet
metal screw) on outside and other two teeth inside
Draft Hood skirt. See Figure 23.
3. Slide mounting bracket tight against lower edge of
Draft Hood skirt. Position #10 sheet metal screw
above skirt's stiffening rib.
4. Secure bracket in position by tightening #10 sheet
metal screw against outer surface of Draft Hood
skirt.
5. Insert excess power cord through Jacket Right Side
Panel hole. Remove slack.
6. Position strain relief bushing around power cord.
Pinch bushing's two halves together and snap back
into hole in Jacket Right Side Panel.
7. Verify power cord, mounting bracket, and Blocked
Vent Switch are secure and located as shown in
Figure 23.
WARNING
Do not operate boiler without Blocked Vent Switch
Properly installed.
Figure 23: Blocked Vent Switch Installation