MODULEX EXT 321, 481, 641, 802, 962, 1123 BOILERS

CHAPTER 3: INSTALLATION INSTRUCTIONS

3.1 General Warnings

3.1.1

Appropriate Use of the Boiler

This boiler MUST be used for the use for which it has been expressively designed. Any other
use shall be considered improper and therefore dangerous.
This boiler is designed to heat water at a temperature below the boiling point at atmospheric
pressure.
3.1.2

Prerequisite System Flushing

Before installing the boiler the following actions MUST be carried out by a competent engineer
or technician:
a) The whole system should be thoroughly flushed in order to remove any
residual dirt or grime which could compromise correct boiler operation.
b) Check that the boiler has been preset for operating with the gas type
available. This is verifiable via the indication on the packaging and on the
data badge;
c) Check that the flue pipe has an adequate draft, does not have any
constrictions or obstructions, and that no other appliance's flue outlets have
been fitted, unless the flue pipe is serving more than one heating appliance,
according to the specific standards and regulations in force. The connection
between the boiler and flue outlet can be made only after this verification has
been carried out.
3.1.3

Installation Personnel Qualifications

The appliance must be installed by a qualified engineer or technician, who complies with the
technical requirements, who, under his own responsibility, guarantees the compliance of the
standards according to the latest regulations.
The appliance must be positioned so that at least the minimum operational and servicing
clearances are provided.
The boiler must be connected to a heating system which is compatible to its performance and
output.
FOR MASSACHUSETTS INSTALLATIONS: The boiler MUST be installed by a plumber or gas
fitter licensed within the Commonwealth of Massachusetts.
3.1.4

Carbon Monoxide Detector Installation

The installation MUST conform to the requirements of the authority having jurisdiction or, in the
absence of such requirements, to one of the following:
United States:
National Fuel Gas Code, ANSI Z223.1/NFPA 54.
Canada: Installation must conform to the requirements of CAN/CSA-
B149.1 - Natural Gas and Propane Installation Code
Where required by the authority having jurisdiction, the installation must
conform to the Standard ASME CSD-1 Controls and Safety Devices for
Automatically Fired Boilers.
OMM-0087_0F
GF-143
Installation, Operation & Maintenance Manual
Installation must conform to the requirements of the
AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913
Phone: 800-526-0288
Page 23 of 146
07/13/15