9/10
Decommissioning/Disposal
9

Decommissioning

9.1

Decommissioning Procedure

10

Disposal

10.1 Disposal / Recycling

24
EcoBlue Plus Combi
CAUTION
Only qualified professionals are authorised to
work on the appliance and system to decommission.
1. If your the boiler needs to be decommissioned either
temporarily or permanently the following should be performed:
Switch off the boiler.
Switch off the boiler's electrical connection.
Close the boiler gas valve.
Drain the CH system.
Seek the advice of your installer.
WARNING
Removal and disposal of the boiler must be carried
out by a qualified installer in accordance with local
and national regulations.