3. WATER PIPING AND CONTROLS

A. BOILER SUPPLY AND RETURN
1. Size the supply and return to suit the system. A
typical piping arrangement is shown in Figure 3.1.
Refer also to the I=B=R Guide - Residential
Hydronic Heating Installation/Design.
2. Return Piping:
Pipe the drain valve to a tee, provided, and the
1-1/4 NPT return tapping near the bottom of the left
section. Pipe the return to the tee. Pipe the drain
valve nipples and tee to the 1-1/4 NPT return
tapping as shown in Figure 3.1.
Figure 3.1: Supply and Return Piping
INSTALLATION AND OPERATING INSTRUCTIONS
3. Supply Piping:
Pipe the supply to the 1-1/2 NPT supply tapping at
the top and rear of the boiler.
4. When system return water temperature will be below
130°F (54°C), pipe the boiler with a bypass
arrangement to blend the system return and hot
supply to obtain at least 130°F (54°C) entering the
boiler.