8.0
Installation – page 19
8.4
Fitting The Boiler
1.
Fit the central heating return filter (Fig. 18) and flow
regulator (Fig. 18a).
2.
Lift the boiler using the lower edges of the combustion
box.
3.
Lift the boiler over the support bracket and engage onto
the top hooks (Fig. 17).
4.
To gain access to the connections between boiler and
valves, release the facia securing screws (¼ turn) and
hinge down the facia box.
5.
Make the gas connection first (Fig. 19). This will
centralise the boiler. The gas sealing washer is an
integral part of the gas tap.
6.
Insert the fibre sealing washers between the valve
outlet face and the flange on the copper bends of the
water circuit connections (Fig. 19).
8.
Tighten the connections.
8.5
Fitting the Pressure Relief Valve and Discharge
Pipe (Fig. 20)
1.
Slacken the grub screw and remove the pressure relief
valve from the adaptor.
2.
Make up the full length of discharge pipe utilising the
tail piece from the kit. The tail piece is to be connected
to the pressure relief valve (See section 6.7).
IMPORTANT: Make all soldered joints before fitting the
pressure relief valve.
3.
Fit the nut and olive from the kit to the discharge pipe
and loosely refit the pressure relief valve to the adaptor.
4.
Tighten the nut and olive on the discharge pipe into the
pressure relief valve. Secure the pressure relief valve
by tightening the grub screw.