SECTION 23—LEAK TEST

4 Way Valve Function Test

NOTE: For this procedure, refer to FIGURE 23.1 on page 77.
The 4‐way valve used in the Perfecto
tolerance of leakage per RexRoth
By nature of the valve design it is possible for the valve to experience small leaks, and still 
operate without affecting the overall performance of the unit. The valve is assembled 
where the components that make up the valve "Snap" together. The only screws in the 
valve are for securing the valve to the manifold assembly.
According to RexRoth there is an acceptable leak specification of 60 cc per minute at 
137.89 kPa (20 p.s.i.) on each valve. Valves that have leaks within this specification will 
function properly without any adverse effects to the performance of the concentrator. A 
leak in the amount of 60 cc or less would be indicative of the type of small leak you would 
notice where the end caps connect to the main body or where the three pieces of the main 
body connect together. A 60 cc leak would not be noticeable when examining the system 
pressure swings. 
Leaks greater than 60 cc are indicative of cracks in the end caps, or a blown seal where the 
end cap connects to the main body of the valve. These leaks are detected by either reading 
the system swing pressures, noticing two consecutive swings not being equal or by 
hearing an audible leak every other cycle. Leaks of this extreme nature indicate the valve 
needs to be replaced.
Valves should only need to be replaced when the following conditions exist:
1. A visible crack is noted on either of the end caps or main body of the 4 way valve, 
regardless of the amount of leak.
2. A large leak is present on the valve that causes an imbalance in the sieve bed swing 
pressures. Example: Sieve Bed 1 pressure swings from 96.52 kPa (14 p.s.i.) to 110.32 
kPa (16 p.s.i.), within 7‐20 seconds and Sieve Bed 2 pressure swings from 89.63 kPa (13 
p.s.i.) to 110.32 kPa (16 p.s.i.) slowly, and may take as long as 25‐30 seconds before 
shifting (times over 30 second will shut down automatically).
3. Valve will not shift and the pilot valve solenoid and circuit board are working 
properly. 
NOTE:  The concentrator's P.C.B. should exhibit an error code for High Pressure Failure (1 RED/
2 GREEN).
NOTE:  The best method to test the 4‐way valve operation is by measuring the unit pressure 
swings. This can easily be done at the HomeFill port with a 0 ‐ 206.84 kPa (0‐30 p.s.i.) pressure 
gauge and a ¼" fill line adapter. Upon starting the unit should build pressure up to 110.32 kPa 
(16 p.s.i.) for output flows 3 L/min and below or 21 p.s.i. for output flows 4 L/min and above before 
its initial shift. After the initial shift the unit should shift consistently in equal amounts of time +/
‐ 1 second (time recorded in seconds).
Perfecto
2
 Series Concentrators does have an acceptable 
2
®
.