INSTALLATION
ASHLIP INSTALLATION
1)
Line up the two holes in the ashlip with the bottom 2 holes in the front of the stove.
2)
Screw into position with the two screws provided with the ashlip.
1)
The trim kit allows for 1/2" (13 mm) of finish facing material. The kit may be installed directly on and/or against standard
combustible building materials.
2)
Frame in the enclosure for the Kit with framing material. The framed opening for the assembled kit is 31.75" (806mm)
high x 37.75" (959mm) wide x 19.5" (495mm) (20" (508mm) including drywall) deep. See diagram below.
3)
For exterior walls, vapour barrier and insulate the enclosure to the same degree as the rest of the house, or according
to local installation codes.
4)
The appliance may be enclosed above the standoffs on the cabinet but the clearances stated on the "B- vent" chimney
must be maintained.
6
NOTE: The bottom gold trim does not go onto
FRAMING
the unit when the ashlip is installed.
U31/I31 Gas Insert Zero Clearance Kit