Planning Checklist

This checklist identifies installation tasks and responsibilities sequentially. If you
have to renovate your site, you will need a longer planning cycle.
Task/Consideration
Checkpoint 1
Designate a person in your organization with the responsibility for all phases
of site preparation.
Review all site planning information with the designated person. Determine
who will actually perform each site preparation task and mark this checklist.
Plan for the installation of the device cables between the devices and the
processor. Before leaving this checkpoint step, turn to Chapter 6, "Cabling
and Connectivity," on page 6-1 and read the information now about planning
for future cable needs and the "zSeries Fiber Cabling Service" on page 6-1
Determine the schedule with your IBM marketing representative. Fill in the
dates on this form.
Identify communication needs and the source for the communication lines.
Identify modem needs.
Checkpoint 2
Lay out the floor plan. Show the locations of the processor, control units,
work stations, modems, power outlets, and accessories. If you are planning
a new computer room, information contained on IBM'sResource Link web
site (http://www.ibm.com/servers/resourcelink) may be helpful. See "General
Information for Planning a Physical Site". If you are planning an installation
on a non-raised floor, ask your marketing representative if your system
requires cables designed to reduce electronic noise interference.
Review the overall site preparation plan.
Place orders for cables. See Chapter 6, "Cabling and Connectivity," on page
6-1
Contact the IBM zSeries Fiber Cabling Service (FCS) for assistance. FCS
will help you plan for the cabling solution that meets your individual system
requirements. Your marketing representative will provide you with the
information necessary to contact FCS.
Checkpoint 3
Determine if the existing programs need changes. Schedule changes as
required.
Determine if any existing devices and control units need changes. Schedule
changes as required.
Arrange for installing the device cables between the work stations,
controllers, and modems.
Arrange for installing the power receptacles and wiring.
Define a training program for employees.
Use Resource Link (http://www.ibm.com/servers/resourcelink) to obtain
required manuals (such as System Overview,IOCP Users Guide,PR/SM
Planning Guide). See your IBM marketing representative for specific
manuals you may need.
Checkpoint 4
Review the progress of the data communication plan. Identify and resolve
any schedule conflicts.
Review the system configuration to ensure the configuration meets your
requirements Make necessary changes.
Checkpoint 5
Review the installation plan and define any points in the schedule that may
cause a problem.
1-2
zSeries 800: Installation Manual for Physical Planning
Level 04a, June 21, 2004
Task Assigned
(check)
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______
_______