IMPORTANT: Condensate trap must be manually
fi lled with water at initial start up.
9-1 Condensate Drain Assembly
2. Reconnect hose to hose
barb with collet clip before
starting boiler.

9 - START UP PROCEDURE

NOTICE
1. Disconnect collet clip from
hose barb and fi ll Condensate
trap with water.
9.1 Fill boiler with water and purge air
Fill boiler with potable water.
Fill boiler and system piping with water (or antifreeze-
water solution, if used). See antifreeze information
page 11. Purge air from boiler using air vent. Purge
air from system piping.
Inspect system piping and boiler connections. Repair
any leaks immediately.
9.2 Fill Condensate Trap with Water
Disconnect collet clip from condensate hose barb. See
fi gure 9-1.
Disconnect tubing below from hose barb.
Pour approximately 2 cups (473 ml) of water into
condensate drain.
Reconnect tubing to hose barb with collet clip. See
fi gure 9-1.